Attendees
Name | Role | Present |
---|---|---|
Remennik, Lyubov | NIH/NCI | |
Safran, Tracy | NIH/NCI [C] | |
Ong, Kim L | NIH/NCI [C] | |
Lucas, Jason R | NIH/NCI [C] | |
Bauer, Scott  | NIH/NCI [C] | |
Alkis, Barry | NIH/NCI [C] | |
Solie, Chuck | NIH/NCI [C] | |
Truong, Tracy | NIH/NCI [C] | |
Kondareddy, Swathi | NIH/NCI [C] | |
Singh, Itendra | NIH/NCI [C] | |
Zhang, Chao | NIH/NCI [C] | |
Johnson, Connie | NIH/NCI [C] | |
Whiteman, Lori | NIH/NCI [C] | |
Benson, Mark | NIH/NCI [C] |
Agenda
EVS Discussion
SYSTEMS | |
---|---|
Systems | Discussion Points:
Decision Points:Â |
LEXEVS UPDATES | |
LexEVS Sprint Status | Current Sprint - Sprint 191 (July 14 – July 27, 2022) 16X237 Agile Development - Sprint Status#16X237AgileDevelopmentSprintStatus-Sprint191
|
LexEVS Spring Updates | Discussion Points:
|
Future Planning | Discussion Points: Â Planning for Mayo team in the coming fiscal year:
|
CTS2 Mapping/URI Resolver | Discussion Points:
Decision Points: |
Statistics Dashboard | Discussion Points:Â
Decision Points: |
Comparison/Mapping Tool | Discussion Points
Decision Points: |
EVS transition to virtual machines | Discussion Points: Decision Points: |
Team Absences | Mayo Team
MSC Leidos
|
Vulnerability testing | See below |
EVS SERVICE AND ARCHITECTURE GROUP UPDATES | |
EVS Service and Architecture Group | Discussion Points: Decision Points: |
DATA UPDATES | |
Data | Discussion Points: July data on Prod. Other monthlies available for review Decision Points: |
Data Deployment Processes | |
BROWSER UPDATES | |
Browser | Discussion Points:
Decision Points: |
QA UPDATES | |
QA | Discussion Points:Â (see chart) Decision Points:Â |
TERMINOLOGIES LIFECYCLE REPORT | |
Terminology Updates and Schedule Discussion Points: Decision Points: | |
Mark asked about DevOps and who controls it. Nobody knew of any teams outside systems. |
LexEVS Spring Migration Progress
Spring Related Update | Estimated Effort | Status |
---|---|---|
Spring Related Update | Estimated Effort | Status |
Ivy Dependency Update | 3 days | Complete |
Ibatis to Mybatis xml conversion | 3 days | Complete |
Compile capable code conversion | 3 days | Complete |
Application context startup | 1 week | Complete |
CodingSchemeDao Verification tests / Code Corrections | 10 days | Complete |
Association Dao Verification tests / Code Corrections | 10 days | Complete |
Registry Dao Verification / Code Corrections | 10 days | Complete |
Coded Node Graph Dao / Code Corrections | 10 days | Complete |
Entity Dao / Code Corrections | 10 days | Complete |
NCI History Dao / Code Corrections | 3 days | Complete |
Property Dao / Code Corrections | 10 days | Complete |
Revision Dao / Code Corrections | 2 days | Complete |
System Release Dao / Code Corrections | 1 day | Complete |
Pick List Dao / Code Corrections | 1 week | Complete |
Pick List Entry Dao / Code Corrections | 1 week | Complete |
Source Asserted Value Set Dao / Code Corrections | 2 days | Complete |
Value Set Definitions Dao / Code Corrections | 10 days | Complete |
Value set Hierarchy Dao / Code Corrections | 1 day | Complete |
Vaue set Definition Entry Dao / Code Corrections | 2 days | Complete |
Value Set Entry State Dao / Code Corrections | 2 days | Complete |
Value Set Property Dao / Code Corrections | 1 week | Complete |
Versions Dao / Code Corrections | 2 days | Complete |
Testing/ Verification | 2 weeks | Complete* |
Load tests | 2 weeks | On Hold |
Testing verification Recoding | 10 days | Partial completion |
Full system test | 1 day | Triaged |
LexEVS Remote | 3-4 weeks | Triaged |
LexEVS CTS2 Service | 2-3 weeks | In progress |
Total Effort (Approximately) | 4-5 months |
Vocabularies Slated for Production
 Terminology Updates and Schedule
Vocabulary Name | Local Name | Version | Arrival Date | Loaded to data-qa DB | Date to Stage | Date to Production |
---|---|---|---|---|---|---|
Vocabulary Name in LexBIG | Short Name | Version identifier | Date the vocabulary arrived for processing | Has the vocabulary been loaded to the data-qa database? | Approximate date the vocabulary version is scheduled to move to staging | Approximate date the vocabulary version is scheduled to move to production |
NCI Thesaurus | NCIt | 22.07d | 07/25/2022 | yes | 07/29/22 | 08/01/22 |
NCIt-HGNC | NCIt-HGNC | July2022 | 07/25/2022 | yes | 07/29/22 | 08/01/22 |
SwissProt | SwissProt | July2022 | 07/25/2022 | yes | 07/29/22 | 08/01/22 |
CanMED | CanMED | Aug2022 | 08/01/22 | yes | 08/03/22 | 08/04/22 |
GO | GO | Aug2022 | 08/01/22 | yes | 08/03/22 | 08/04/22 |
HGNC | HGNC | Aug2022 | 08/01/22 | yes | 08/03/22 | 08/04/22 |
MED-RT | MED-RT | Aug2022 |
QA Schedule and Status
SECTION FOR FUNCTIONAL SYSTEM TESTING STATUS ::
Application and Version | Percentage Complete | Estimated Completion Date per Iteration | Priority Level | Type Of Testing | Current Tier for Release (DEV, QA, Stage, Prod) | Expected Production Date |
EVS REST API (v1.6) | 100% | 5/27/2022 | High | Progression + Regression | QA | 6/6/2022 |
EVS Explore (v1.6) | 100% | 5/27/2022 | High | Progression + Regression | QA | 6/6/2022 |
EVS REST API(v1.6) | 100% | 6/1/2022 | High | Regression | Stage | 6/6/2022 |
EVS Explore(v1.6) | 100% | 6/2/2022 | High | Regression | Stage | 6/7/2022 |
EVS REST API(22.05e) - Monthly Data Deployment | 100% | 6/1/2022 | High | Regression | Stage | 6/3/2022 |
EVS REST API(22.05e) - Monthly Data Deployment | 100% | 6/3/2022 | High | Regression | Production | 6/3/2022 |
EVS REST API(v1.6) | 100% | 6/6/2022 | High | Regression | Production | 6/6/2022 |
EVS Explore(v1.6) | 100% | 6/7/2022 | High | Regression | Production | 6/7/2022 |
NCIt,NCIm,TermForm(22.05e + GO & HGNC Jun 2022 Deployment) | 100% | 6/3/2022 | High | Regression | Stage | 6/6/2022 |
NCIt,NCIm,TermForm(22.05e + GO & HGNC Jun 2022 Deployment) | 100% | 6/6/2022 | High | Regression | Production | 6/8/2022 |
EVS REST API(22.06d) - Monthly Data Deployment | 100% | 6/30/2022 | High | Regression | Stage , Production | 6/30/2022 |
NCIt,NCIm,TermForm(22.06d) - Monthly Data Deployment | 100% | 7/8/2022 | High | Smoke | Stage,Production | 7/8/2022 |
NCIt,NCIm,TermForm(22.05e + GO & HGNC Jun 2022 Deployment) | 100% | 6/3/2022 | High | Regression | Stage | 6/6/2022 |
NCIt,NCIm,TermForm(22.06d) - Monthly Data Deployment | 100% | 7/8/2022 | High | Smoke | Stage,Production | 7/8/2022 |
NCIt,NCIm,TermForm(ChEBI, GO & HGNC July 2022 Deployment) | 100% | 7/12/2022 | High | Smoke | Stage | 7/12/2022 |
NCIt,NCIm,TermForm(ChEBI, GO & HGNC July 2022 Deployment) | 100% | 7/13/2022 | High | Smoke | Production | 7/13/2022 |
EVS REST API(22.07d) - Monthly Data Deployment | 100% | 7/27/2022 | High | Regression | Stage , Production | 7/27/2022 |
NCIt,NCIm,TermForm(22.07d) - Monthly Data Deployment | 100% | 8/1/2022 | High | Smoke | Stage,Production | 8/1/2022 |
NCIt,NCIm,TermForm(CanMED, GO & HGNC AUG 2022 Deployment) | 100% | 8/3/2022 | High | Smoke | Stage,Production | 8/3/2022 |
EVS REST API - 1.6.1 (Hot Fix Deployment) | 100 % | 8/3/2022 | Highest | Progression + Regression | Stage,Production | 8/4/2022 |
EVS REST API(22.08e) - Monthly Data Deployment | 100% | 8/31/2022 | High | Regression | Stage , Production | 8/31/2022 |
NCIt,NCIm,TermForm(Metadata 202208 Deployment) | 100% | 8/31/2022 | High | Smoke | Stage,Production | 9/6/2022 |
NCIt,NCIm (2022-09-02.1-v2.17 & 2022-09-02.1-v2.19) | 100% | 9/28/2022 | Low | Progression + Regression | QA,Stage,Production | 9/27/2022 |
EVS REST API - 22.09d - Monthly Data Deployment | 100% | 9/28/2022 | High | Regression | QA,Stage,Production | 9/28/2022 |
NCIt,NCIm,TermForm(22.09d Monthly Data Deployment) | 100% | 10/11/2022 | High | Regression | Stage,Production | 10/11/2022 |
NCIt,NCIm,TermForm(Vocabulary Deployment in GO(Sep2022),HGNC(Oct2022),OBI(2022-07-11),OBIB(2021-11-12)) | 100% | 10/18/2022 | High | Regression | Stage,Production | 10/19/2022 |
NCIt (Tag: 2022-10-07.1-v2.19) | 100% | 10/21/2022 | High | Progression + Regression | QA,Stage | 11/2/2022 |
LexEVS CTS2 Tag (CTS2_srvice 2.0.0.RC5 ) | 100% | 10/24/2022 | High | Progression + Regression | QA | 10/28/2022 |
Report Exporter Regression (Spring Library Updates) | 100% | 10/26/2022 | High | Regression | QA | 2/7/2023 |
EVS REST API - 22.10e - Monthly Data Deployment | 100% | 11/1/2022 | High | Regression | Stage,Production | 11/1/2022 |
NCIt,NCIm,TermForm(22.10e DDR) | 100 % | 11/9/2022 | High | Regression | Stage,Production | 11/16/2022 |
NCIt(2022-11-04.1-v2.19) | 100% | 11/9/2022 | High | Progression + Regression | QA,Stage,Production | 11/28/2022 |
NCIt,NCIm,TermForm(Vocabulary Deployment in CanMED Nov2022,ChEBI v219,GO Nov2022,HGNC Nov2022) | 100% | 11/22/2022 | High | Regression | Stage,Production | 11/22/2022 |
EVS REST API - 22.11d - Monthly Data Deployment | 100% | 11/29/2022 | High | Regression | QA,Stage,Production | 11/29/2022 |
NCIm(2022-12-01.1-v2.17) | 100% | 12/7/2022 | Medium | Progression + Regression | QA | 1/5/2023 |
NCIt,NCIm,TermForm(22.11d DDR) | 100% | 12/6/2022 | High | Sanity | Stage,Production | 12/6/2022 |
NCIt,NCIm,TermForm(23.01e DDR) | 100% | 2/14/2023 | High | Sanity | Stage,Production | 2/14/2023 |
Enterprise Release 1.7 (EVS REST API & EVS Explore) | 54% | 1/25/2023 | High | Progression + Regression (Multiple Iterations) | QA | |
JIRA Issues
Recent EVS Stats Dashboard Related Bugs and Features (within last week)
Recent Report Exporter Related Bugs and Features (within last week)
Recent LexEVS Related Bugs and Features (within last week)
Recent CTS2 Service Related Issues (within last week)
6.5 LexEVS Related Issues
6.5 CTS2 Service Related Issues