Description | Actions, Update | |
---|---|---|
EVS Explore URL updates to evsexplore-stage.semantics.cancer.gov on Stage tier | Cuong was able to confirm the receipt of the new certificate that will be needed for the domain name change. He will coordinate with our Cloud engineers to apply the new cert to the Stage ALB and make any necessary adjustments to the Stage virutalhost configuration file (mirroring what Tracy did earlier for the Dev tier). | |
NCI-RITM0433861 | Requesting update to the Term Browser Jenkins project |
SYSTEMS | |
---|---|
Systems | Working with Systems team is in transition
Slowly working through list of open tickets, the list of "Open System Tickets" is proving very useful. Thanks for keeping it updated ! |
LEXEVS UPDATES | |
Future Planning | Planning for April - EVS Plans for April 2023.png
|
LexEVS Sprint Status | Current Sprint - Sprint 205 (Apr 10 - Apr 24 2023) 16X237 Agile Development - Sprint Status#16X237AgileDevelopmentSprintStatus-Sprint204
|
Technical Debt remediation |
|
caDSR Query | Discussion Points: |
Statistics Dashboard | Discussion Points:
Decision Points: |
Comparison/Mapping Tool | Plan is to update product roadmap by end of April. Mark is working on user stories and requirements |
EVS transition to virtual machines | Status: ON HOLD
Reference: Wiki page: Server Migration 2021 |
Report Exporter |
|
AWS Cloud to be in Separate Account | Discussion Points
Decision Points: |
Team Absences | Mayo Team - Andrew - April 27 - May 1 MSC - Leidos - (Mark out Friday morning till 2pm - 4/14) Systems - |
EVS SERVICE AND ARCHITECTURE GROUP UPDATES | |
EVS Service and Architecture Group | Discussion Points: Decision Points: |
DATA UPDATES | |
Data | Discussion Points:
Decision Points: |
BROWSER UPDATES | |
Browser |
|
QA UPDATES | |
QA | Discussion Points: (see chart)
Decision Points: |
TERMINOLOGIES LIFECYCLE REPORT | |
Terminology Updates and Schedule Discussion Points: Decision Points: | |
Mark Benson TPM Update | No updates |
LexEVS Technical Debt Progress
Technical Debt Related Update | Estimated Effort | Start Date | Complete Date | Status | JIRA | ADO Ticket |
---|---|---|---|---|---|---|
Code Inventory | 4 days | 12/20/22 | 1/30/23 | Complete | 2037998 | |
Lexevs - update "easy" jars | 2 days | 1/31/23 | 2/13/23 | Complete | LEXEVS-5319 | 2111723 |
Update ddlutils - research and design | 3 days | 2/2/23 | 2/15/23 | Complete | 2122958 | |
Update ddltils - implementations | 10 days | 2/15/23 | 3/8/23 | Complete | 2141127 | |
Lexevs Unit testing | 2 days | 3/8/2023 | In Progress | LEXEVS-5325 | 2141156 | |
CTS2 lexevs-service vulnerability update | 2 days | 3/13/2023 | 3/20/23 | Complete | 2141189 | |
CTS2 unit testing | 2 days | 3/20/23 | 4/5/23 | Complete | LEXEVS-5326 | 2141198 |
QA Lexevs / CTS2 | 3 days | 4/12/23 | In Progress | LEXEVS-5327 | 2141217 | |
Repair QA issues | 2 days | on hold | ||||
Deployment Lexevs / CTS2 | 5 days (elapsed) | on hold | LEXEVS-5328 | 2141227 | ||
LexEVS Corretta Java 8 testing | 3 days | 4/6/23 | In Progress | LEXEVS-5331 | ||
CTS2 Corretta Java 8 testing | 1 day | 4/6/23 | In Progress | LEXEVSCTS2-433 | ||
lexevs remaining dependency updates - design | 10 days | 4/10/23 | In Progress | LEXEVS-5333 | ||
lexevs remaining dependency updates - implementation | 20 days | LEXEVS-5334 | ||||
lexevs remaining dependency updates - unit testing | 2 days | LEXEVS-5335 | ||||
CTS2 remaining dependency updates - design | 1 day | LEXEVSCTS2-435 | ||||
CTS2 remaining dependency updates - implementation | 3 days | LEXEVSCTS2-436 | ||||
CTS2 Unit testing | 2 days | LEXEVSCTS2-437 | ||||
QA | 2 days | LEXEVSCTS2-438 LEXEVS-5336 | ||||
Deployment | 5 days (elapsed) | |||||
lexevs-service-rest-docs vulnerability update design | 2 days | LEXEVSCTS2-440 | ||||
lexevs-service-rest-docs vulnerability implementation | 4 days | LEXEVSCTS2-441 | ||||
lexevs-service-rest-docs unit testing | 1 day | LEXEVSCTS2-442 | ||||
lexevs-service-rest-docs QA | 1 day | LEXEVSCTS2-443 | ||||
lexevs-service-rest-docs deployment | 4 days (elapsed) | |||||
lexevs-service-rest-docs Java 8 testing | 2 days | |||||
Total Effort (Approximately) | 104 days |
Technical Debt Related Update | Estimated Effort | Status |
---|---|---|
Report Exporter vulnerabilities - design | 4 days | |
Report Exporter vulnerabilities - implementation | 5 days | |
Unit testing | 2 days | |
QA | 2 days | |
Deployment | 5 days (elapsed) |
Vocabularies Slated for Production
Terminology Updates and Schedule
Vocabulary Name | Local Name | Version | Arrival Date | Loaded to data-qa DB | Date to Stage | Date to Production |
---|---|---|---|---|---|---|
Vocabulary Name in LexBIG | Short Name | Version identifier | Date the vocabulary arrived for processing | Has the vocabulary been loaded to the data-qa database? | Approximate date the vocabulary version is scheduled to move to staging | Approximate date the vocabulary version is scheduled to move to production |
NCI Thesaurus | NCIt | 23.03d | 03/27/2023 | yes | ||
NCIt-HGNC | NCIt-HGNC | Mar2023 | 03/27/2023 | yes | ||
SwissProt | SwissProt | Mar2023 | 03/27/2023 | yes | ||
MetaThesaurus | META | 202302 | 03/13/2023 | yes | 03/29/23 | 03/31/23 |
QA Schedule and Status
SECTION FOR FUNCTIONAL SYSTEM TESTING STATUS ::
Application and Version | Percentage Complete | Estimated Completion Date per Iteration | Priority Level | Type Of Testing | Current Tier for Release (DEV, QA, Stage, Prod) | Expected Production Date |
EVS REST API (v1.6) | 100% | 5/27/2022 | High | Progression + Regression | QA | 6/6/2022 |
EVS Explore (v1.6) | 100% | 5/27/2022 | High | Progression + Regression | QA | 6/6/2022 |
EVS REST API(v1.6) | 100% | 6/1/2022 | High | Regression | Stage | 6/6/2022 |
EVS Explore(v1.6) | 100% | 6/2/2022 | High | Regression | Stage | 6/7/2022 |
EVS REST API(22.05e) - Monthly Data Deployment | 100% | 6/1/2022 | High | Regression | Stage | 6/3/2022 |
EVS REST API(22.05e) - Monthly Data Deployment | 100% | 6/3/2022 | High | Regression | Production | 6/3/2022 |
EVS REST API(v1.6) | 100% | 6/6/2022 | High | Regression | Production | 6/6/2022 |
EVS Explore(v1.6) | 100% | 6/7/2022 | High | Regression | Production | 6/7/2022 |
NCIt,NCIm,TermForm(22.05e + GO & HGNC Jun 2022 Deployment) | 100% | 6/3/2022 | High | Regression | Stage | 6/6/2022 |
NCIt,NCIm,TermForm(22.05e + GO & HGNC Jun 2022 Deployment) | 100% | 6/6/2022 | High | Regression | Production | 6/8/2022 |
EVS REST API(22.06d) - Monthly Data Deployment | 100% | 6/30/2022 | High | Regression | Stage , Production | 6/30/2022 |
NCIt,NCIm,TermForm(22.06d) - Monthly Data Deployment | 100% | 7/8/2022 | High | Smoke | Stage,Production | 7/8/2022 |
NCIt,NCIm,TermForm(22.05e + GO & HGNC Jun 2022 Deployment) | 100% | 6/3/2022 | High | Regression | Stage | 6/6/2022 |
NCIt,NCIm,TermForm(22.06d) - Monthly Data Deployment | 100% | 7/8/2022 | High | Smoke | Stage,Production | 7/8/2022 |
NCIt,NCIm,TermForm(ChEBI, GO & HGNC July 2022 Deployment) | 100% | 7/12/2022 | High | Smoke | Stage | 7/12/2022 |
NCIt,NCIm,TermForm(ChEBI, GO & HGNC July 2022 Deployment) | 100% | 7/13/2022 | High | Smoke | Production | 7/13/2022 |
EVS REST API(22.07d) - Monthly Data Deployment | 100% | 7/27/2022 | High | Regression | Stage , Production | 7/27/2022 |
NCIt,NCIm,TermForm(22.07d) - Monthly Data Deployment | 100% | 8/1/2022 | High | Smoke | Stage,Production | 8/1/2022 |
NCIt,NCIm,TermForm(CanMED, GO & HGNC AUG 2022 Deployment) | 100% | 8/3/2022 | High | Smoke | Stage,Production | 8/3/2022 |
EVS REST API - 1.6.1 (Hot Fix Deployment) | 100 % | 8/3/2022 | Highest | Progression + Regression | Stage,Production | 8/4/2022 |
Attendees
Name | Role | Present |
---|---|---|
Remennik, Lyubov | NIH/NCI | |
Safran, Tracy | NIH/NCI [C] | |
Ong, Kim L | NIH/NCI [C] | |
Lucas, Jason R | NIH/NCI [C] | |
Bauer, Scott | NIH/NCI [C] | |
Alkis, Barry | NIH/NCI [C] | |
Solie, Chuck | NIH/NCI [C] | |
Truong, Tracy | NIH/NCI [C] | |
Kondareddy, Swathi | NIH/NCI [C] | |
Singh, Itendra | NIH/NCI [C] | |
Zhang, Chao | NIH/NCI [C] | |
Johnson, Connie | NIH/NCI [C] | |
Whiteman, Lori | NIH/NCI [C] | |
Benson, Mark | NIH/NCI [C] | |
Andrew Moore | NIH/NCI [C] |