Date
Attendees
Name | Attended |
---|---|
Jayashree Kalpathy-Cramer | |
Ulli Wagner | Yes |
Carolyn Klinger | Yes |
Benjamin Bearce | Yes |
Currently supported challenges
Name of Challenge | Organization / Meeting | Medici instance used | Release | Release Validation data | Release Test data | Number of Participants | Closing Date | Will the challenge remain open? | Comments |
---|---|---|---|---|---|---|---|---|---|
SIRPRISE Reconstruction Challenge | https://www.aapm.org/GrandChallenge/SIRPRISE/ | https://medici-codalab-main.eastus.cloudapp.azure.com/ | Submitters will upload images to Medici. Did decide not to use FTP transfer but upload zipped images directly to Codalab. It was found out that the data size is not as large as anticipated. | ||||||
Truth-based CT reconstruction challenge | https://medici-codalab-main.eastus.cloudapp.azure.com/ | submitters will upload images to Dropbox, organizers will provide the scoring. Ben will create entries for each participants and enter the scores so that they can be shown on the leaderboard. | |||||||
DL-sparse challenge #2 | Ben is talking with Emil about using MedICI again for another DL-Sparse challenge |
Previously supported challenges that remain open
Name of Challenge | Organization / Meeting | Medici instance used | Release | Release Validation data | Release Test data | Number of Participants | Closing Date | Will the challenge remain open? | Comments |
---|---|---|---|---|---|---|---|---|---|
Tasks / Deliverables
Task | Due Date | Deliverable | Status | |
---|---|---|---|---|
Supporting at least three challenges including one federated learning challenge | 8/30/2022 | |||
Support organizers and participants (help desk, FAQ, training, presentations) | 8/30/2022 | |||
Maintain and update the website | 8/30/2022 | |||
Capturing and providing metrics on the use of the MedICI website | 8/30/2022 | |||
Capturing and providing metrics on the challenges | 8/30/2022 | |||
Support at least three previously executed challenges | 8/30/2022 | |||
MedICI on the NCI Cloud Two (GCP) and Firecloud | 8/30/2022 | Task was suspended per discussion on | ||
Operations and Maintenance | 8/30/2022 | |||
Discussion items
Time | Item | Who | Notes |
---|---|---|---|
Notes | |||
Action items |
| ||
Meeting with Codalab developers | Ben is attending meetings. He is helping with fixing bugs. Ben to review the federated learning tasks and discuss with Codalab team. Python3 | ||
Responses to question about keeping challenges open | Unknown User (bearceba) - investigate options on how to keep challenges open, add phase or copy challenge, avoid having users add to the previous submissions SPIE-AAPM-NCI DAIR Digital Breast Tomosynthesis Lesion Detection Challenge (DBTex) - Phase 1 - Unknown User (bearceba) verify with submitters that decision of phase 2 applies to phase 1 SPIE-AAPM-NCI-DAIR & SPIE-AAPM-NCI-DAIR Phase 2 - TBD - (Nick Konz, Wed 11/24/2021 11:36 AM) "Maciej and I discussed this and an idea that we’ve been floating is to have some sort of ongoing validation phase, that would allow anyone to get validation results on their model. We would also want to have a periodic, occasional test phase for people to get test results. BMMR2 - close on as previously planned. (David Newitt, Thu 10/28/2021 7:10 PM) - link to the challenge data will be de-activated on 12/1/2021. DL Sparse - keep open (Emil Sidky, Thu 10/28/2021 11:42 PM) MICCAI 2020 - has already an open test phase ISBI 2018 - has already an open test phase AAPM RT-MAC Challenge - is open-ended | ||
Upcoming challenges | MIDRC classification challenge (frontal/lateral views) AAPM - SIPRISE challenge - Diane Alvares, Baptist Health. She filled out the submission form and sent instructions. TrueCT - Truth-based CT reconstruction challenge - is being setup. Submitters need to upload images (30 GB per submission). Ben is investigating what the best method is e.g. submission to the cloud. Several options were discussed. Google workspace. | ||
Information sharing | Ben established connection with developers of Codalab/Codabench. He will join their meeting and potentially take a more active role in product development. These activities can be charged to the contract. | ||
Monthly status reports | due on the 10th day of the following month | ||
Contract / invoice status / SOW |
| ||
Paper | The draft will be submitted by September 15, 2020. - Not received | ||
Videos |
| ||
Federated learning challenge - proposal for MICCAI, ACR confirmed that the data can be used Wagner, Ulrike (NIH/NCI) [C] Change SOW, take cloud out, put federated learning modifications for Codalab in, send to Medici for review | |||