Lead: Joshua Phillips and Bea Mahious

Attendees

Team Member

Organization

Dave Hau

NCI CBIIT

Greg Raley

NCI CBIIT

Denis Advic

NCI CBIIT

Raghu Chintal

NCI CBIIT

Joshua Phillips

SemanticBits

Beate Mahious

SemanticBits

Patrick McConnell

SemanticBits

Ram Chilukuri

SemanticBits

Tom Digre

SemanticBits

Alan Blair

SemanticBits

Meeting Agenda

1. Review of Sprint 1

2. Planning Sprint 2

Meeting Minutes

1. Review of Sprint 1

Joshua Phillips reviewed the project plan, deliverables, and milestones - we are on track

Items that went well and went poorly:

  • Joshua: we didn't get the team together quickly enough, made good progress on the UML modeling, we should be able to reuse the approach to ECCF that the caEHR team is taking
  • Tom: prototype came along more slowly than expected because the technology stack was a little bit in flux, made good progress on modeling, BDA does not yet support OSGI target development
  • Patrick: we were slow to get the vision/scope together, progress too slow on SRS and Use Cases, but content good; wiki content and structure is good, but thinks that the ECCF templates are not finalized
  • Beate: would have liked to spend more time to go through planning meetings so that we have exact dates and timelines for future meetings/tasks, it is good that we are integrating with the Con Ops team, great progress on UML/prototype, good to merge with caDSR team early
  • Ram: more planning meetings would have been helpful to flesh out items, good progress overall
  • Alan: new to the team
  • Dave: we are a little behind in the project plan, some of this is a moving target (like ECCF), we should communicate more with other specification teams (like w/ Raghu on ECCF), we may need to interpret these standards to fit our needs (e.g. ECCF), need to keep an Agile mindset and process due to the nature of the project

2. Planning Sprint 2

Jira will be used for task tracking

  • We should keep an eye on the Jira deployment at NCI to make sure we are compatible when it comes online
  • A weekly export to SVN should not be a problem
  • Everyone should log in and select the tasks they can complete in this sprint

Requirements will be covered more by use cases than activity diagrams (per experience with caEHR project)
We will need to define specifically what the interoperability inter-registry requirements are in order to determine the standards to select
Our requirements and use cases should not focus on current functionality, but instead desired functionality

-> See attachment for Sprint 2 backlog.

Action Items

Name Responsible

Action Item

Date Due

Notes

Bea Mahious

enter Sprint 2 backlog into JIRA and inform software engineers to pick their own tasks for Sprint 2.

3/31/2010

done

Bea Mahious

Talk to Kumar about weekly export to SVN

4/2/2010