EVS Weekly Tech Meeting

Discussion Points:

  • LexEVS
    • Lexevs 6.5 AnthillPro migration to Jenkins update on upper tiers.
      • Migrations completed:
        • Lexevs API (Dev, QA, Stage, Prod)
        • Lexevs-service (CTS2) (Dev, QA)
      • Migrations not yet completed:
        • Lexevs-service (CTS2) (Stage, Prod)
          • We need to wait for the term browser to go at the same time so we have compatible releases.
          • There will be some downtime when setting up Prod.
        • URI Resolver (Dev, QA, Stage, Prod)
      • Goal is to be off from AHP by end of this year.
    • Lexevs-system tests (Jenkins/Docker) system failures causing builds to fail.
    • Lexevs URLs for 6.5.1
  • Browser/Tools
  • Data
  • Systems
  • Triple Store/EVS API

Decision Points:

Roll Call 

Sprint Status

 

Current Sprint  Sprint 83 (May 24, 2018 – June 6, 2018)

16X237 Agile Development - Sprint Status#16X237AgileDevelopment-SprintStatus-Sprint83

Release Roadmap
  • Discussion Points:
    • Planned Release Roadmap
      • Estimated effort:
        • Sprint 83 - May 24, 2018 June 6, 2018
          • LexEVS will be code complete during this sprint. 
          • Last planned snapshot (SNAPSHOT.15) will be delivered during this sprint.
          • Anticipated delivery of SNAPSHOT.15 by about May 30th.
          • Deploy SNAPSHOT.15 to Dev.
        • Sprint 84 - June 7, 2018 - June 20th
          • If no issues were found in SNAPSHOT.15 on Dev, we can re-brand SNAPSHOT.15 as a release candidate (RC1) and deploy to QA for testing (on or after June 7).  

Decision Points:

Mapping Namespace Issue

Discussion Points:

  • Jira
    serverNCI Tracker
    columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
    serverId7954a81f-12da-3366-a0ef-97c806660e7c
    keyLEXEVS-3748

Decision Points:

EVS F2F Planning

Discussion Points:

Decision Points:

LexEVS External Users

Discussion Points:

Decision Points:

Team Absences

Mayo Team

  • Cory - June 5, June 18th - 21st
  • Scott - June 18th - July 1st, July 25 -27
  • Craig -

NCI

  • Tracy - June 7, July 30 - August 5
  • Rob - June 28,29, July 12,13
  • Bron -