The following table contains the high-level project deliverables and associated timelines


Task/MilestoneDateResponsibility

Identify and finalize the CDISC SHARE files for curation activities.

Completed

CBIIT

Curate CDASH Domain in caDSR. 

Completed

CBIIT

Build CDASH Domain forms in the caDSRFormBuilder.

Completed

CTSU 

Import caDSRCDASH Domain Forms into Rave via the OCI.

12/10/18

CTSU 

Build Rave GLIB.

January 2019

CTSU 

Update CTEP-AERS per CDISC requirements

*in  parallel with CTSU activities

CTIS 

Create CDISC Rave Global Library (GLIB) ALS.

February 15, 2019

CTSU 

Perform compliance review on the CDISC Rave GLIB ALS.

Feb 22nd, 2019

CDSIC PM 

Beta Release CDISC-compliant OPEN ALS v7.0. *Timeline dependent on CDISC SME Support

March 31st, 2019

CTSU

CDSIC PM 

Beta Release CDISC-compliant Rave-CTEP-AERS Integration ALS v4.0. *Timeline dependent on CDISC SME Support

March 31st, 2019

CDSIC PM

Perform CDISC Rave GLIBImpact Analysis.

March/April 2019

LPO 

Manage IA updates to CDISC Rave GLIB.

April/May 2019

CTSU

Release CDISC Rave GLIB  ALS to LPOs. 

Build Seed Study in
  collaboration with CDISC SME


 

Jul 2019


 

CTSU, 

CTSU, CDISC PM