  1. When you receive an email notification to review one or more projects, click the link in that message. The Manage Review page appears, listing all of your active projects. You can also access this page by selecting Manage > Review

    The Manage Review page.Image Modified

    (TBD: I'll recapture this if anything in it changes, such as "Select all" button, icon for selection column, Data Curator column, or First/Last buttons.)

  2. To display all projects (both active and completed), click Display Completed Projects. For additional instructions, refer to Filtering, Sorting, and Navigating the List of Projects - 2021-05-27

    Show If
    groupGP-CFW-DMEDOC-DEV, GP-CFW_ADMINS
    Panel
    borderColorsilver
    borderStylesolid
    titleVisible to Internal Users Only

    To send a reminder manually: In the Data Curator column, click the curator's name. The Notifications dialog box appears. Click the resend icon (The resend icon.). 

  3. In the first column, click the row for the project you want to review. A check mark appears in that column for that row. You can select multiple projects, but the system will apply the same values to all of the selected projects. To select all rows in the list, click Select All.  
  4. Click Review. The Update Project dialog box appears.

    The Update Project dialog box.

  5. (Optional) For active projects, you can change the project status. 
  6. (Optional) Specify pre-publication link or PubMed link for publications, if any. For example:
    • Court et al, Science, 359, 339-343, Dec 21 2016
    • PMID:30065725
    • Commun Biol. 2019 Oct 4;2:358. doi: 10.1038/s42003-019-0604-2. eCollection 2019.
  7. (Optional) Specify the deposition (the repository in which this data has been deposited), if any. For example:
    • dbGaP
    • GDC
  8. If you have changed the status of a project from active to completed, specify the retention period in years (up to ten).

    The Update Project dialog box for a completed project.Image Removed

    (TBD: I'll recapture this if anything in it changes, such as "Retention Years" label.)

    Once you click Update, you will not be able to change the status or retention period settings again in the Update Project dialog box.

  9. Click Update. The system responds as follows:
    • If you have changed the status of a project from active to completed, the system calculates the sunset date based on the number of retention years you specified and the current date. 