Technical Debt Related Update | Estimated Effort | Start Date | Complete Date | Status | JIRA | ADO Ticket |
---|---|---|---|---|---|---|
Code Inventory | 4 days | 12/20/22 | 1/30/23 | Complete | 2037998 | |
Lexevs - update "easy" jars | 2 days | 1/31/23 | 2/13/23 | Complete | 2111723 | |
Update ddlutils - research and design | 3 days | 2/2/23 | 2/15/23 | Complete | 2122958 | |
Update ddltils - implementations | 10 days | 2/15/23 | 3/8/23 | Complete | 2141127 | |
Lexevs Unit testing | 2 days | 3/8/2023 | In Progress | LEXEVS-5325 | 2141156 | |
CTS2 lexevs-service vulnerability update | 2 days | 3/13/2023 | 3/20/23 | Complete | 2141189 | |
CTS2 unit testing | 2 days | 3/20/23 | 4/5/23 | Complete | LEXEVS-5326 | 2141198 |
QA Lexevs / CTS2 | 3 days | on hold | LEXEVS-5327 | 2141217 | ||
Repair QA issues | 2 days | on hold | ||||
Deployment Lexevs / CTS2 | 5 days (elapsed) | on hold | LEXEVS-5328 | 2141227 | ||
LexEVS Corretta Java 8 testing | 3 days | 4/6/23 | In Progress | LEXEVS-5331 | ||
CTS2 Corretta Java 8 testing | 1 day | 4/6/23 | In Progress | LEXEVSCTS2-433 | ||
lexevs-system-test design | 4 days | |||||
lexevs-system-test implementation | 6 days | |||||
lexevs remaining dependency updates - design | 10 days | 4/10/23 | In Progress | |||
lexevs remaining dependency updates - implementation | 20 days | |||||
CTS2 remaining dependency updates - design | 1 day | |||||
CTS2 remaining dependency updates - implementation | 3 days | |||||
Unit testing | 2 days | |||||
QA | 2 days | |||||
Deployment | 5 days (elapsed) | |||||
lexevs-service-rest-docs vulnerability update design | 2 days | |||||
lexevs-service-rest-docs vulnerability implementation | 4 days | |||||
lexevs-service-rest-docs unit testing | 1 day | |||||
lexevs-service-rest-docs QA | 1 day | |||||
lexevs-service-rest-docs deployment | 4 days (elapsed) | |||||
lexevs-service-rest-docs Java 11 design | 2 days | |||||
lexevs-service-rest-docs Java 11 implementation | 3 days | |||||
lexevs-service-rest-docs unit testing | 1 day | |||||
lexevs-service-rest-docs QA | 1 day | |||||
Total Effort (Approximately) | 104 days |
...