Page History
...
SYSTEMS | |
---|---|
Systems | Discussion Points:
Decision Points: |
LEXEVS UPDATES | |
LexEVS Sprint Status | Current Sprint - Sprint 197 (Oct 12 – Oct 26 2022) 16X237 Agile Development - Sprint Status#16X237AgileDevelopmentSprintStatus-Sprint194
|
Future Planning | Discussion Points: Planning for Mayo team in the coming fiscal year:
|
CTS2 Mapping/URI Resolver | Discussion Points:
Decision Points: |
caDSR Query | Review requirements for caDSR query |
Statistics Dashboard | Discussion Points:
Decision Points: |
Comparison/Mapping Tool | Discussion Points:
Decision Points: |
EVS transition to virtual machines | Discussion Points:
Decision Points: |
Report Exporter | Discussion Points:
Decision Points: |
AWS Cloud to be in Separate Account | Discussion Points
Decision Points: |
Team Absences | Mayo Team
MSC Leidos |
EVS SERVICE AND ARCHITECTURE GROUP UPDATES | |
EVS Service and Architecture Group | Discussion Points: Decision Points: |
DATA UPDATES | |
Data | Discussion Points:
Decision Points: |
BROWSER UPDATES | |
Browser | Discussion Points:
Decision Points: |
QA UPDATES | |
QA | Discussion Points: (see chart)
Decision Points: |
TERMINOLOGIES LIFECYCLE REPORT | |
Terminology Updates and Schedule Discussion Points: Decision Points: | |
Mark Benson TPM Update |
|
LexEVS Spring Migration Progress
...
Spring Related Update
...
Estimated Effort
...
Spring Related Update | Estimated Effort | Status |
---|---|---|
Ivy Dependency Update | 3 days | Complete |
Ibatis to Mybatis xml conversion | 3 days | Complete |
Compile capable code conversion | 3 days | Complete |
Application context startup | 1 week | Complete |
CodingSchemeDao Verification tests / Code Corrections | 10 days | Complete |
Association Dao Verification tests / Code Corrections | 10 days | Complete |
Registry Dao Verification / Code Corrections | 10 days | Complete |
Coded Node Graph Dao / Code Corrections | 10 days | Complete |
Entity Dao / Code Corrections | 10 days | Complete |
NCI History Dao / Code Corrections | 3 days | Complete |
Property Dao / Code Corrections | 10 days | Complete |
Revision Dao / Code Corrections | 2 days | Complete |
System Release Dao / Code Corrections | 1 day | Complete |
Pick List Dao / Code Corrections | 1 week | Complete |
Pick List Entry Dao / Code Corrections | 1 week | Complete |
Source Asserted Value Set Dao / Code Corrections | 2 days | Complete |
Value Set Definitions Dao / Code Corrections | 10 days | Complete |
Value set Hierarchy Dao / Code Corrections | 1 day | Complete |
Vaue set Definition Entry Dao / Code Corrections | 2 days | Complete |
Value Set Entry State Dao / Code Corrections | 2 days | Complete |
Value Set Property Dao / Code Corrections | 1 week | Complete |
Versions Dao / Code Corrections | 2 days | Complete |
Testing/ Verification | 2 weeks | Complete* |
Load tests | 2 weeks | On Hold |
Testing verification Recoding | 10 days | Complete |
Full system test | 1 day | Triaged |
LexEVS Remote | 3-4 weeks | Triaged |
LexEVS CTS2 Service | 2-3 weeks | Complete |
LexEVS CTS2 Service | 2 weeks | Complete |
LexEVS CTS2 Deployment | 2 days | Complete |
Browser Deployment Debug | 1 week | Pull request in |
QA | 2 weeks | |
Total Effort (Approximately) | 4-5 months |
...