Project

Goal

Assigned to

Accomplished?

1ICDC/CTN

Preplan the ATO



2ICDCExplore D3 to display animated charts, heatmaps and graph representations

3ICDCPush/Pull data from/to Cloud Resources

4ICDCCreate Study Detail page

5ICDCGet two widgets functioning: Program/Studies & Gender/Neutered Status

6ICDCDeploy Stage environment


Retrospective Results

What went well

...

What could have gone better?


DescriptionAuthor
If we change the ticket description, it needs to be updated in the ticket - just using the comments isn't sufficient.
Changes in scope need to go up the chain to ensure that the entire sprint is in scope - just because something can be done easily now, doesn't mean that it should be done ahead of something harder.


Tickets


MVP Sprint 8


Jira
serverNCI Tracker
columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
maximumIssues20
jqlQuerysprint=1853
serverId7954a81f-12da-3366-a0ef-97c806660e7c

...