Sprint Status

 

Current Sprint  Sprint 35 (July 21, 2016 – August 3, 2016)

LexEVS 6.4 S13-500 Agile Development - Sprint StatusStatus#SprintStatus-Sprint35

Tracy is working on Data deployment to DEV and QA

The indexes were created on DEV.  These indexes will need to be propagated to QA.  Tracy will be doing this move.

We closed out Sprint 35.

Tasks associated to the 6.4 release have been closed.

We will create a build that has the OWL2 loader changes.  This will be done in the next sprint

QA Tier Status

  • NCI-RITM0031271: New container on QA for the LexEVS 6.4 Remote API
  • NCI-RITM0031282: CTS2 AHP on QA
  • AppScan

LexEVS Remote API and LexEVS service (CTS2) have been deployed to QA.

Larry approved the test plan.

Tin will start the testing on QA. 

Next, the AppScan will be submitted.

LexEVS using HTTPs - Update

  • LexEVS - no impact
  • CTS2 - no impact / configuration
  • Remote API - changes needed
  • URI Resolver - no impact / configuration

Remote API - the client will need to change based on SSL changes.

Because the Remote  API client will need to change, we decided to not update LexEVS 6.3.  Instead, we will add the HTTPs  ability to LexEVS 6.4 and not LexEVS 6.3.

TODO: Cory will need to add a warning message that Remote clients will need to use SSL.  This should be added the notes about how to upgrade from LexEVS 6.4 to LexEVS 6.4.

 

Java 8 and Spring 4 update - not needed

We have found that the current versions of Java 8 and our current Spring 2.x are building and testing with one issue with CTS2.  Deepak will investigate further.

Deepak is using Java 8.92 in the Docker system test scripts.

LexEVS is running Spring 2.x.  At some point this should be updated to Spring 4.

Larry suggested the Mayo team should investigate the quickest path to getting the Remote API set up for HTTPs.

Tracy suggested that we have an HTTPs fix by the end of August.  The Mayo team will investigate to see if this is possible.

At this point we will not upgrade to Spring 4.

Priority for upgrades (in this order): HTTPs, CentOS 7, Java 8.

LexEVS 6.4.0 testing will continue and will be pushed up the tiers.

We will put the HTTPs changes only into LexEVS 6.4.1.  No Java upgrade.

Jacob/Tracy/Sarah can be contacted for configuration on DEV

TODO: We need to get an announcement on this change to users as soon as we understand the impact and the wiki updated for this.

 Data issues on ProdThis has been discussed and there is a plan is in place.
 6.5 PlanningCraig will explain the changes in detail next week when the board is completed.

LexEVS External Users

Brian added a couple comments to the issue.

Scott will follow up with some additional suggestions.

Team Absences

Mayo Team

  • Deepak - Sept 1-6?, Sept 5
  • Cory - August 5, 12, Sept 5
  • Scott - Sept 5
  • Craig - August 24 -29, Sept 5

...