EVS Discussion


SYSTEMS
Systems

Discussion Points:

Decision Points:


LEXEVS UPDATES

LexEVS Sprint Status


  • To meet soon to discuss ADO vs Jira reporting
    • Ticket in for Snehal to have access to Jira
      • Kevin Burns added Snehal today
      • Snehal waiting for contact
    • Add column to report table for start date of task
  • Vue3 Updates for Report Exporter nearing completion
  • Working on updating browser for Spring 5 - on dev
  • About 95% work on vulnerabilities in LexEVS
    • CTS2 to follow
Future Planning

Discussion Points:

 Planning for Mayo team in the coming fiscal year:

  • Java 8 migration to 11
    • EOL Sep '23
      • Corretta Java8 extends through 2026.
    • Waiting for info on migration deadlines
    • Implications for Tomcat containers
    • JREs available on servers
      • New VMs will be created to support
  • EVS Compare
Technical Debt remediation

LexEVS Code Debt Refactoring

  • Code inventory for Java migration
    • Work begun on implementationNeed risk assessment of the work - what is the risk of NOT doing things
  • Vulnerable dependencies
    • Work on lexevs nearing completion
    • CTS2 next up
  • Java 8 to 11
    • To discuss next week with Cuong
  • Other dependencies

CTS2 Mapping/URI Resolver

Discussion Points:

Decision Points:

caDSR Query

Discussion Points:

Statistics Dashboard

Discussion Points: 

  • Google analytics - Retiring GA and going to GA4
    • May need to only update GA, not applications. 
      • Need further experimentation, documentation
      • Per Kim - looks like scripts need to be updated from GA3 to GA4
        • Double check all parties notified
    • No analytics being collected by EVS Explore
    • Add to Report Exporter and EVS Compare
      • EVS Exporter working - check for ticket
      • Create token for EVS Compare - though it is not ready to gather yet
  • Sumo Logic issues
    • Metrics report due this week

Decision Points:

Comparison/Mapping Tool

Discussion Points:

Decision Points:

EVS transition to virtual machines

Discussion Points:

  • Server Migration 2021
    • QA2
      • QA 1 retirement
    • Stage 
      • Instance of VM instantiated. Needs configuration. 
      • Blocker: Waiting to hear from Systems on what is needed to progress, if they have configuration information.
      • Followed by Prod then DataQA
    • Need to improve accountability and communications
    • Subsumed by Java 11 migration?
      • Discuss with Cuong

Decision Points:

Report Exporter

Discussion Points:

  • Tomcat and Spring Vulnerability noted on the Report Exporter
    • Deployed on Prod
  • Working on update to Vue3 (JavaScript Framework). EVSREPEXP-451
    • Due: Mar 10 (end of sprint 205); on week 14 of estimated 16
    • master ticket: EVSREPEXP-442 - Migrate Vue.js version from 2.0 to 3.0
    • Description
      • On Dev and being regression tested
      • Working on rebuilding

        1. Select Concept Codes for Entity Export - 80% complete
        2. Select Properties - 90% complete
        3. Formatted export - 100%
  • GA3 to GA4 migration
  • Vulnerable dependencies

Decision Points:

AWS Cloud to be in Separate Account

Discussion Points

  • No Response as of yetFrozen

Decision Points:

Team Absences


Mayo Team - 

MSC -

Leidos - 

Systems - 


EVS SERVICE AND ARCHITECTURE GROUP UPDATES
EVS Service and Architecture Group

Discussion Points:

  • Remote API and URI Resolver retirement
    • Looking at 3 months after announcement - April timeframe June?
    • Need an announcement sent out ahead of time
      • Announcement sent out with NCIt release
      • Test of APIs shows lexevsapi65 working, lexevsapi not. No action needed.

Decision Points:


DATA UPDATES
Data

Discussion Points: 

  • 23.02d - actively debugging issue with value set loading
  • QA to be discussed Thursday morning

Decision Points:


BROWSER UPDATES

Browser

Discussion Points:

  • Nothing this weekKim is monitoring and responding to issues with value set loading

Decision Points: 


QA UPDATES

QA

Discussion Points:  (see chart)

Decision Points: 

  • Completed Stage testing on EVSExplorer and EVS Rest API
  • Software deployed to Prod but indexes need to complete before testing.

Decision Points: 



TERMINOLOGIES LIFECYCLE REPORT

Terminology

TERMINOLOGIES LIFECYCLE REPORT

Terminology Updates and Schedule 

Discussion Points: 

Decision Points: 

Mark Benson TPM Update

We're tracking Service tickets in a spreadsheet (in Sharepoint) to better see how long tickets are taking to get resolved.

The Link has been shared, if there are any issues accessing, please let Mark know.TPM Update

Spreadsheet: EVS Service Tickets.xlsx

...

Technical Debt Related Update

Estimated Effort

Start Date

Complete Date

Status

ADO Ticket

Code Inventory4 days12/20/221/30/23Complete2037998
Lexevs - update "easy" jars2 days1/31/232/13/23Complete2111723
Update ddlutils - research and design3 days2/2/232/15/23Complete2122958
Update ddltils - implementations10 days2/15/233/8/23Complete2141127
Lexevs Unit testing2 days3/8/2023
In Progress2141156
CTS2 lexevs-service vulnerability update2 days


2141189
CTS2 unit testing2 days


2141198
QA Lexevs / CTS2

3 days




2141217
Repair QA issues2 days



Deployment Lexevs / CTS25 days (elapsed)


2141227
Update LexEVS to Java 11 - research and design4 days


2152899
LexEVS Java 11 implementation5 days


2152917
lucene 9 - research and design8 days


2145025
lucene 9 - implementation15 days


2145027
LexEVS Java 11 unit testing3 days


2152921
CTS2 lexevs-service Java 11 - research and design 3 days


2152928
CTS2 lexevs-service Java 11 implementation3 days


2152932
CTS2 unit testing2 days


2152941
QA Lexevs / CTS2

3 days




2152945
Repair QA issues2 days


2153023
Update Jenkins1 day


2152947
Deployment Lexevs / CTS210 days (elapsed)


2152950
lexevs-service-rest-docs vulnerability update design2 days



lexevs-service-rest-docs vulnerability implementation4 days



lexevs-service-rest-docs unit testing1 day



lexevs-service-rest-docs QA

1 day





lexevs-service-rest-docs deployment4 days (elapsed)



lexevs-service-rest-docs Java 11 design

2 days





lexevs-service-rest-docs Java 11 implementation3 days



lexevs-service-rest-docs unit testing1 day



lexevs-service-rest-docs QA

1 day





lexevs-system-test design4 days



lexevs-system-test implementation6 days



lexevs remaining dependency updates - design10 days



lexevs remaining dependency updates - implementation20 days



CTS2 remaining dependency updates - design1 day



CTS2 remaining dependency updates - implementation3 days



Unit testing2 days



QA2 days



Deployment5 days (elapsed)



Total Effort (Approximately)104 days



...