Technical Debt Related Update

Estimated Effort

Start Date

Complete Date

Status

JIRA

ADO Ticket

Code Inventory4 days12/20/221/30/23Complete
2037998
Lexevs - update "easy" jars2 days1/31/232/13/23Complete
2111723
Update ddlutils - research and design3 days2/2/232/15/23Complete
2122958
Update ddltils - implementations10 days2/15/233/8/23Complete
2141127
Lexevs Unit testing2 days3/8/2023
In ProgressLEXEVS-53252141156
CTS2 lexevs-service vulnerability update2 days3/13/20233/20/23Complete
2141189
CTS2 unit testing2 days3/20/234/5/23CompleteLEXEVS-53262141198
QA Lexevs / CTS2

3 days

on hold

LEXEVS-53272141217Repair QA issues2 daysDeployment Lexevs / CTS25 days (elapsed)2141227Update LexEVS to Java 11 - research and design4 days2152899LexEVS Java 11 implementation5 days2152917lucene 9 - research and design8 days2145025lucene 9 - implementation15 days2145027LexEVS Java 11 unit testing3 days2152921CTS2 lexevs-service Java 11 - research and design 3 days2152928CTS2 lexevs-service Java 11 implementation3 days2152932CTS2 unit testing2 days2152941QA Lexevs / CTS2

3 days

2152945
Repair QA issues2 days2153023Update Jenkins1 day2152947on hold



Deployment Lexevs / CTS210 5 days (elapsed)on hold


2141227
LexEVS Corretta Java 8 testing3 days4/6/23
In Progress

CTS2 Corretta Java 8 testing1 day4/6/23
In Progress2152950

lexevs-service-rest-docs vulnerability update design2 days




lexevs-service-rest-docs vulnerability implementation4 days




lexevs-service-rest-docs unit testing1 day




lexevs-service-rest-docs QA

1 day






lexevs-service-rest-docs deployment4 days (elapsed)




lexevs-service-rest-docs Java 11 design

2 days






lexevs-service-rest-docs Java 11 implementation3 days




lexevs-service-rest-docs unit testing1 day




lexevs-service-rest-docs QA

1 day






lexevs-system-test design4 days




lexevs-system-test implementation6 days




lexevs remaining dependency updates - design10 days




lexevs remaining dependency updates - implementation20 days4/10/23
In Progress

CTS2 remaining dependency updates - design1 day




CTS2 remaining dependency updates - implementation3 days




Unit testing2 days




QA2 days




Deployment5 days (elapsed)




Total Effort (Approximately)104 days




...