NIH | National Cancer Institute | NCI Wiki  

WIKI MAINTENANCE NOTICE

Please be advised that NCI Wiki will be will be undergoing maintenance on Monday, June 24th between 1000 ET and 1100 ET.
Wiki will remain available, but users may experience screen refreshes or HTTP 502 errors during the maintenance period. If you encounter these errors, wait 1-2 minutes, then refresh your page.

If you have any questions or concerns, please contact the CBIIT Atlassian Management Team.

Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Ticket Description Actions, Update

NCI-RITM0520059/NCI-SCTASK0867247

CTS2 down on Dev and QA
Met with Systems team to debug on Tu, Feb 27.
Ticket entered to install visual VM to track stack on Visual VM working Dev

NCI-RITM0512149

Security consult about IP traffic to Prod
Asked for dynamic IP throttling
Working to escalate using WAF (Web Application Firewall)
Mark to keep close eye on this

 NCI-RITM0524607

Add DataDog collectors to Prod2 server

Pinged today to check status

NCI-RITM0514215Remove Extensions folder from Stage and Prod

Pinge ticket to check statusComplete

MultipleRequests to remove all DataDog SumoLogic collectors

Systems working on this


Mount point failures on jenkins

Affects ftp updates.


Data Deployments to Dev and QA


EVS transition to virtual machines

STATUS:

  • Prod2 server up and running - completed tested
  • DATAQA next


  • Tomcat 8.5 reached EoL - needing new stacks for all tiers
    • Oracles OES8, Tomcat 10, Java 17 
      • Java 17 implemented
      • Others to follow once 17 on Pro
    • Options
      • Tomcat 9 and Java 17 installed on Dev
      • evs-jenkins working for NCItBrowser and lexevscts2
      • OES8 could come later
    • NCItermform installed on Dev - needs testing
  • Stage 2 - all upgrade
  • Prod 2 - all upgrade
    • OEL8 needed
  • Kathy Coleman watching the progress
  • Tomcat 9 installed on Dev.  
    • Jenkins complete for NCItBrowser and CTS2
    • Recoding needed for NCIm
    • NCI Term Form needs testing
  •  Check status of termform and Tomcat9 - 
  •  Meeting scheduled Thursday for Visual VM



LEXEVS UPDATES

Monthly Planning and Focus

Completed Sprint - Sprint 219 (Mar 5 - May 10) -

Current Sprint  - Sprint 220 (May 13 - May 31) - 

For the month of May 2024

Technical Debt remediation
LexEVS Code Debt Refactoring - Java 17 refactoring currently is in progress
  • Tomcat 9 installed on Dev.  
    • Jenkins complete for NCItBrowser and CTS2
    • Recoding needed for NCIm
    • NCI Term Form needs testing
Report Exporter
  • Working on templating starting
    • Doing phase 1 - moved to Stage
      • Code not being accepted on search - same tag as QAStage EVS Rest API having issues
      • Cloud team addressing the issue
    • In progress: implement file-based template storage
      • Code completed
      • On Dev issue with Rest APi affecting testing - working currently
        • Tomcat 9 testing - working with systems to find resolution
        • Having trouble moving page to page - possible http/https conflict
    • Moving Dev and QA to run from 7AM-10PM


Security

Tomcat 8.5 is EOL - risk if new vulnerability discovered

  • Oracle Java 8 - still being used on DataQA
    • Still present on other servers, in $PATHTracy to put in tickets - once data out for May
    • Java 17 being added next week
  • Protege servers are on Oracle Java 8now Corretto on Dev and QA
    • Need to check upper tiers

Statistics Dashboard

OBJECTIVE 
Complete Migration of Statistics Dashboard from SumoLogic to DataDog by March June 1 2024.  Hard end in April (ish) - possibly end of June  

STATUS

  • S3 bucket has been created
    • Working on integration
    • successfully tested refresh
    • need to operationalize - testing going on today
  • Collectors installed on all servers 
    • Apache config complete
  • Apache logs being pulled in for p805
    • evs.cancer.gov now working
      • EVSRESTAPI/EVSExplorer - fixed
      • FTP1 downloads - needs tweaking.fixed
  • Prod 2 collectors installed, need pipelines
  • New Dashboards being made - can be shared

Link: Sharepoint Project Task Checklist

Comparison/Mapping Tool

On Hold

  • Moved to 7-10
  • shutdown to save resources?
    • Is old architecture so needs update work if kept
    • Per Lyubov - can shut down server for now
AWS Cloud to be in Separate Account

Waiting on AWS team

Team Absences


Mayo Team - Scott working vacation late May - Starting May 16, Andrew June 17-23

MSC - 

Leidos - 

QA - 

Gov - Memorial Day Monday May 27



EVS SERVICE AND ARCHITECTURE GROUP UPDATES
EVS Service and Architecture Group

Discussion about migrations and status.

DataQA to be rebooted to update OS


DATA UPDATES
Data
  • NCIt published last week
  • Monthlies are on Stage and being tested. Prod this week 

BROWSER UPDATES

Browser
  •  Possibly reboot NCIt every morning? Idea rejected
  • This week has been calm

QA UPDATES

QA
  • Prod Deployment testing for the NCIt completed 24.04e
  • Monthlies being tested on Stage
  • Ad hoc testing on NCIt and NCIm last week for migrations 

TERMINOLOGIES LIFECYCLE REPORT

Terminology Updates and Schedule 

Mark Benson TPM UpdateCBIIT to AWS connection physically cut a few days ago.  Issues have been occurring since then.


Vocabularies Slated for Production

...