Risks

Opened DateDue DateDescriptionLikelihood (H, M, L)ImpactAssignedStatusMitigation Strategy Comments
 1 7/17/2014 

Based on initial analysis of the Protégé the move to Web Protégé may prove to be prohibitively expensive

 HSchedule will slip and cost will go upKumar KuntipuramClosed

Work with vendors to keep solution cost low or look for alternative solutions.

 Resolved
 2 7/17/2014 

Key personnel leave the project during POP

 LSchedule will slipKumar KuntipuramClosed

Provide supportive subcontractor management; work with Leidos TPM and NCI GPM to identify replacement personnel

 Resolved
 37/17/2014 

Contract deliverables or interim releases not meeting the timeline requirements per SOW.

 MSchedule will slipKumar KuntipuramClosed

Work with stakeholders to identify issues, track, analyze and resolve them.  Establish a schedule for project  deliverables; communicate with project team at each meeting to ensure team is meeting the planned schedule.

 Resolved

Comments Issues

 #Opened DateDescriptionImpactAssignedStatus
      
      
      

Dependencies

Opened DateDescriptionAssigned
   
   
   