Attendance

NameRoleOrganizationPresent (Y/N)
Kumar KuntipuramTPM Leidos 
Sherri De CoronadoGSCBIIT 
Gilberto FragosoSME

CBIIT

 
Bob DionneSubcontract PM

Dionne Associates

 
Tin TranQA Leidos  
Sichen LiuGPMCBIIT  

Action Items

Create Project Plan

 #AssignedDescriptionDate IdentifiedDue DateDate Completed CommentsStatus
 1Kumar Kuntipuram Update SOW with new tasks and submit for mod1/8/2015  5/1/20154/27/2015 

 1/14/2015: Received additional task information and corresponding personals for the mod. Currently being evaluated

1/28/2015: Started work on mod documents

3/30/2015: Mod completed and sent to vendor for signature

5/6/2015: Mod executed.

Closed
 2Gilberto, Kumar Verify status of production tech stack upgrade 1/8/2015  4/24/20154/24/2015 

1/28/2015: Awaiting systems to update server

3/5/2015: Upgrade proceeding

3/30/2015: Production setup completed and undergoing testing

5/6/2015: Some performance issues, but application in production. Issue being investigated

Closed
 3Kumar Kuntipuram Work with QA and dev to explore possibilities of automation and CI for Protégé.2/5/2015  5/30/2015 

2/12/2015: Provided QA with Protégé application to run and familiarize. QA also exploring tools for desktop application automation.

3/6/2015: QA continuing to explore available tools for desktop applications.

5/6/2015: Tool called Marathon Testing identified and will be purchased after stakeholder approval. Will explore CI after tool has been purchased.

In Progress

Progress

Area of InterestDetails
WikiUpdated Project Status Wiki
ProductionProduction online
 ModMod executed
 QATool identified and recommended 

JIRA Issues

Issue NumberDescriptionStatus
   
   
   

Project Plan Changes

#DescriptionDue DateResourcesNotesRisksMitigation
       
       
       

 Planned Activities

Area of InterestDetails
QAComplete Protégé test plan and cases 
MODSubmit cost mod to the contracts 

Risks, Issues, Dependencies

Risks, Issues & Dependencies

 