Sprint 41
- Dates: October 13, 2016 – October 26, 2016 (2 weeks)
- Goal:
- Provide tier deployment support.
- Build 6.4.1.1 fix.
- 6.5 planning and development.
- Provide continued support and issue resolution.
- Project Roadmap
- TBD
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
Sprint 40
- Dates: September 29, 2016 – October 12, 2016 (2 weeks)
- Goal:
- Provide tier deployment support.
- 6.5 planning and development.
- Provide continued support and issue resolution.
- Project Roadmap
- Agile Board
- Sprint Report (includes issues/deliverables)