Goals


Goal

Assigned to

Accomplished?

1Nifi vs. PentahoPhil
2

Build out lab component of data model

Phil/Mark


3Bulk up on dataPhil


4Test graph vs. postgres/graph (cont'd)Mark
5Specify vocabulary for BRIDGMark
6Start Data Ingestion DesignAmit
7

GitHub Training

Amit
8Transform data from one S3 bucket to anotherAmit
9Define data model constraints (stretch goal)Phil
10Define staffing planMatt


Retrospective Results

AuthorCategoryCard Title
Matthew BWhat WorkedYe is excited about semantics integration.
Matthew BWhat WorkedTeam energy erupted around new direction towards end of sprint.
Amit MWhat Didn't WorkSudden change in direction was unexpected. Lack of the 'Big Demo' made it hard for some members in maintaining continuity
Matthew BWhat Didn't WorkPhil can't take anymore time off.  He blocked Mark from getting any work done.
Matthew BSuggestions for ImprovementData stack page as part of overall site, listing guiding principles, docker, turnkey instances, github references, built in semantics, etc. - Data Commons in a Box.
Matthew BSuggestions for ImprovementMake sure Matt is invited to all meetings, even if not expected to attend, and meeting leader should provide a 2-3 sentence summary at end of meeting.
Amit MSuggestions for ImprovementNeed a more clear vision moving forward for the team both short term and long term.
Matthew BSuggestions for ImprovementToolkit, Continuous data integration potentiated by native graph database engines
Amit MWhat WorkedTeam rallied around changed circumstances. Good collaborative engagement.


Tickets

Sprint 4


Key Summary T Created Updated Due Assignee Reporter P Status Resolution