Goals
Goal | Assigned to | Accomplished? | |
---|---|---|---|
1 | Nifi vs. Pentaho | Phil | |
2 | Build out lab component of data model | Phil/Mark | |
3 | Bulk up on data | Phil | |
4 | Test graph vs. postgres/graph (cont'd) | Mark | |
5 | Specify vocabulary for BRIDG | Mark | |
6 | Start Data Ingestion Design | Amit | |
7 | GitHub Training | Amit | |
8 | Transform data from one S3 bucket to another | Amit | |
9 | Define data model constraints (stretch goal) | Phil | |
10 | Define staffing plan | Matt |
Retrospective Results
Author | Category | Card Title |
---|---|---|
Matthew B | What Worked | Ye is excited about semantics integration. |
Matthew B | What Worked | Team energy erupted around new direction towards end of sprint. |
Amit M | What Didn't Work | Sudden change in direction was unexpected. Lack of the 'Big Demo' made it hard for some members in maintaining continuity |
Matthew B | What Didn't Work | Phil can't take anymore time off. He blocked Mark from getting any work done. |
Matthew B | Suggestions for Improvement | Data stack page as part of overall site, listing guiding principles, docker, turnkey instances, github references, built in semantics, etc. - Data Commons in a Box. |
Matthew B | Suggestions for Improvement | Make sure Matt is invited to all meetings, even if not expected to attend, and meeting leader should provide a 2-3 sentence summary at end of meeting. |
Amit M | Suggestions for Improvement | Need a more clear vision moving forward for the team both short term and long term. |
Matthew B | Suggestions for Improvement | Toolkit, Continuous data integration potentiated by native graph database engines |
Amit M | What Worked | Team rallied around changed circumstances. Good collaborative engagement. |
Tickets