The following table contains the high-level project deliverables and associated timelines
Task/Milestone | Date | Responsibility |
---|---|---|
Identify and finalize the CDISC SHARE files for curation activities. | Completed | CBIIT |
Curate CDASH Domain in caDSR. | Completed | CBIIT |
Build CDASH Domain forms in the caDSRFormBuilder. | Completed | CTSU |
Import caDSRCDASH Domain Forms into Rave via the OCI. | 12/10/18 | CTSU |
Build Rave GLIB. | January 2019 | CTSU |
Update CTEP-AERS per CDISC requirements | *in parallel with CTSU activities | CTIS |
Create CDISC Rave Global Library (GLIB) ALS. | February 15, 2019 | CTSU |
Perform compliance review on the CDISC Rave GLIB ALS. | Feb 22nd, 2019 | CDSIC PM |
Beta Release CDISC-compliant OPEN ALS v7.0. *Timeline dependent on CDISC SME Support | March 31st, 2019 | CTSU CDSIC PM |
Beta Release CDISC-compliant Rave-CTEP-AERS Integration ALS v4.0. *Timeline dependent on CDISC SME Support | March 31st, 2019 | CDSIC PM |
Perform CDISC Rave GLIBImpact Analysis. | March/April 2019 | LPO |
Manage IA updates to CDISC Rave GLIB. | April/May 2019 | CTSU |
Release CDISC Rave GLIB ALS to LPOs. Build Seed Study in | Jul 2019 | CTSU, CTSU, CDISC PM |