Attendees
Name | Role | Present |
---|---|---|
Remennik, Lyubov | NIH/NCI | |
Safran, Tracy | NIH/NCI [C] | |
Ong, Kim L | NIH/NCI [C] | |
Lucas, Jason R | NIH/NCI [C] | |
Bauer, Scott | NIH/NCI [C] | |
Alkis, Barry | NIH/NCI [C] | |
Solie, Chuck | NIH/NCI [C] | |
Truong, Tracy | NIH/NCI [C] | |
Kondareddy, Swathi | NIH/NCI [C] | |
Singh, Itendra | NIH/NCI [C] | |
Zhang, Chao | NIH/NCI [C] | |
Johnson, Connie | NIH/NCI [C] | |
Whiteman, Lori | NIH/NCI [C] | |
Benson, Mark | NIH/NCI [C] |
Agenda
EVS Discussion
SYSTEMS | |
---|---|
Systems | Discussion Points: Decision Points: |
LEXEVS UPDATES | |
LexEVS Sprint Status | Current Sprint - Sprint 191 (July 14 – July 27, 2022) 16X237 Agile Development - Sprint Status#16X237AgileDevelopmentSprintStatus-Sprint191
|
LexEVS Spring Updates | Discussion Points:
|
Future Planning | Discussion Points: Planning for Mayo team in the coming fiscal year:
|
CTS2 Mapping/URI Resolver | Discussion Points:
Decision Points: |
Statistics Dashboard | Discussion Points:
Decision Points: |
Comparison/Mapping Tool | Discussion Points
Decision Points: |
EVS transition to virtual machines | Discussion Points: Decision Points: |
Team Absences | Mayo Team
MSC Leidos
|
Vulnerability testing | See below |
EVS SERVICE AND ARCHITECTURE GROUP UPDATES | |
EVS Service and Architecture Group | Discussion Points: Decision Points: |
DATA UPDATES | |
Data | Discussion Points: Decision Points: |
Data Deployment Processes | |
BROWSER UPDATES | |
Browser | Discussion Points:
Decision Points: |
QA UPDATES | |
QA | Discussion Points: (see chart) Decision Points: |
TERMINOLOGIES LIFECYCLE REPORT | |
Terminology Updates and Schedule Discussion Points: Decision Points: | |
Mark asked about DevOps and who controls it. Nobody knew of any teams outside systems. |
LexEVS Spring Migration Progress
Spring Related Update | Estimated Effort | Status |
---|---|---|
Spring Related Update | Estimated Effort | Status |
Ivy Dependency Update | 3 days | Complete |
Ibatis to Mybatis xml conversion | 3 days | Complete |
Compile capable code conversion | 3 days | Complete |
Application context startup | 1 week | Complete |
CodingSchemeDao Verification tests / Code Corrections | 10 days | Complete |
Association Dao Verification tests / Code Corrections | 10 days | Complete |
Registry Dao Verification / Code Corrections | 10 days | Complete |
Coded Node Graph Dao / Code Corrections | 10 days | Complete |
Entity Dao / Code Corrections | 10 days | Complete |
NCI History Dao / Code Corrections | 3 days | Complete |
Property Dao / Code Corrections | 10 days | Complete |
Revision Dao / Code Corrections | 2 days | Complete |
System Release Dao / Code Corrections | 1 day | Complete |
Pick List Dao / Code Corrections | 1 week | Complete |
Pick List Entry Dao / Code Corrections | 1 week | Complete |
Source Asserted Value Set Dao / Code Corrections | 2 days | Complete |
Value Set Definitions Dao / Code Corrections | 10 days | Complete |
Value set Hierarchy Dao / Code Corrections | 1 day | Complete |
Vaue set Definition Entry Dao / Code Corrections | 2 days | Complete |
Value Set Entry State Dao / Code Corrections | 2 days | Complete |
Value Set Property Dao / Code Corrections | 1 week | Complete |
Versions Dao / Code Corrections | 2 days | Complete |
Testing/ Verification | 2 weeks | Complete* |
Load tests | 2 weeks | On Hold |
Testing verification Recoding | 10 days | Partial completion |
Full system test | 1 day | Triaged |
LexEVS Remote | 3-4 weeks | Triaged |
LexEVS CTS2 Service | 2-3 weeks | In progress |
Total Effort (Approximately) | 4-5 months |
Vocabularies Slated for Production
Terminology Updates and Schedule
Vocabulary Name | Local Name | Version | Arrival Date | Loaded to data-qa DB | Date to Stage | Date to Production |
---|---|---|---|---|---|---|
Vocabulary Name in LexBIG | Short Name | Version identifier | Date the vocabulary arrived for processing | Has the vocabulary been loaded to the data-qa database? | Approximate date the vocabulary version is scheduled to move to staging | Approximate date the vocabulary version is scheduled to move to production |
NCI Thesaurus | NCIt | 22.07d | 07/25/2022 | yes | 07/29/22 | 08/01/22 |
NCIt-HGNC | NCIt-HGNC | July2022 | 07/25/2022 | yes | 07/29/22 | 08/01/22 |
SwissProt | SwissProt | July2022 | 07/25/2022 | yes | 07/29/22 | 08/01/22 |
CanMED | CanMED | Aug2022 | 08/01/22 | yes | 08/03/22 | 08/04/22 |
GO | GO | Aug2022 | 08/01/22 | yes | 08/03/22 | 08/04/22 |
HGNC | HGNC | Aug2022 | 08/01/22 | yes | 08/03/22 | 08/04/22 |
MED-RT | MED-RT | Aug2022 |
QA Schedule and Status
JIRA Issues