What did we do well?

  • All committed stories were completed within the Sprint.
  • Exit Criteria was well documented and satisfied.
  • Logging of hours is better this Sprint - but still no good way to review hours logged for tasks/person.  
  • Team did well despite travel and competing activities. 

What should we have done better?

  • When estimating the sprint (hours) we need to include and consider admin time (sprint planning), PTO, and then 7/1 work time.
  • Need to determine how to get better/more efficient responses from NCI. 
  • For tasks that need to have NCI review, do not include that step in the exit criteria.  This will be outside of our tasks. 