NIH | National Cancer Institute | NCI Wiki  

 Attendees

NameRolePresent
Wright, Larry NIH/NCI   
Fragoso, Gilberto NIH/NCI     

De Coronado, Sherri    

NIH/NCI    

Safran, Tracy

NIH/NCI    
Ong, Kim L
IS 
Lucas, Jason R
IS 
Bauer, Scott  Mayo 
Peterson, Kevin
Mayo 
Stancl, Craig
Mayo 
Wynne, Robert    NIH/NCI 
Brem, Larry  NIH/NCI [C]   
Pan, JJ
NIH/NCI [E] 
Tran, Tin    NIH/NCI [C]  
Kanjamala, Pradip  Mayo  
Ahmed, Shamim
NIH/NC [C]  
Haber, Margaret (NIH/NCI) 
Roth, Laura (NIH/NLM)  
Ramani, Vivek (NIH/NCI) [C]  
Carlsen, Brian (NIH/NCI) [C] 
Wong, Joanne   

Kuntipuram, Kumar

  

 

Action Items

 #AssignedDescriptionDate IdentifiedDue DateDate CompletedStatus
39KevinDemo of REST service exposed in Mayo value set browser   deferred
53CraigUpdate the project plan according to Tin's schedule   done
54TracyWill try the NCI Thesaurus again.  To follow up with Scott if this continues to load slowly.  Will also test the new MedDRA load features. LexEVS-569 (NCIt took 22 hours to load).  MedDRA load completed and needs examined  09/24/2013done
55PradipPradip to get a lexbig.jar to Kim   done
56ScottProvide PTE Links to Tin for URI Resolver and CTS2 Service   done
57KimUpdate JIRA item 581 and set to deferred   done
59ScottContact Tracy about the details of the MedDRA active/inactive status implementation   open
60ScottCommit an interim fix for the Thesaurus xml export   done
61RobTo get files for Scott to do test load of the NCI Thesuarus   done
62Kevin/ScottTo coordinate getting content from third party for wiki update   open
63KevinInitiate discussion for Mayo on JIRA item #585   open
64ScottCommunicate to Craig on the possible government shutdown.   done
64KevinTo follow up on URI's on OWL2 with Harold.   open
65GilbertoTo let Mayo know when SFTP site goes live   done

Progress

Area of InterestDetails
Loader Evaluation statusMedDRA
6.1 QA and Deployment (Scott) 
JIRA #492 (Scott)XML Exporter update
Release artifacts (Gilberto)Where will these artifacts be kept (formerly uploaded to Gforge). Gilberto waiting for a reply from the support about the SFTP site.  Nearly ready to go live.
Thesaurus load time (Scott) 
JIRA #585Question open on the '?' search for contains. Mayo will discuss and respond with analysis of implementation.  (Kevin)
Govt Shutdown Actiities

Update Documentation - Scott

    ◦    Base URL
    ◦    Install Options page (need final deployment)
    •    Prepare for LexEVS development (Complete) - Cory
    •    Tracy problem with XML exporter (Jira 492  LEXEVS-492 - Getting issue details... STATUS ) - Scott/Cory
    •    MIF loader issues (identified by Tracy and Gilberto) - Scott
    ◦    Need to create Jira items to capture the loader issues.  
    •    JIRA cleanup and prioritization (100 issues) - Scott, Craig, Cory
    •    JIRA 6.1 cleanup - Craig

 

 

JIRA Issues

Description
LEXEVS-570 - Getting issue details... STATUS
LEXEVS-572 - Getting issue details... STATUS
LEXEVS-573 - Getting issue details... STATUS
LEXEVS-574 - Getting issue details... STATUS
LEXEVS-576 - Getting issue details... STATUS
LEXEVS-579 - Getting issue details... STATUS
LEXEVS-583 - Getting issue details... STATUS
LEXEVS-584 - Getting issue details... STATUS
LEXEVS-585 - Getting issue details... STATUS
LEXEVS-586 - Getting issue details... STATUS
LEXEVS-587 - Getting issue details... STATUS
LEXEVS-588 - Getting issue details... STATUS
LEXEVS-589 - Getting issue details... STATUS

Project Plan Changes

#DescriptionDue DateResourcesNotesRisksMitigation
 None     
       
       

 Planned Activities

Area of InterestDetails
  

Risks, Issues, Dependencies

Risks

Opened DateDue DateDescriptionLikelihood (H, M, L)ImpactAssignedStatusMitigation Strategy
         
         
         

Issues

 #Opened DateDescriptionImpactAssignedStatus
      
      
      

Dependencies

Opened DateDescriptionAssigned
   
   

 

 

 

 

  • No labels