Agenda
EVS Discussion
SYSTEMS | |
---|---|
Systems | Discussion Points:
Decision Points: |
LEXEVS UPDATES | |
LexEVS Sprint Status | Current Sprint - Sprint 204 (Feb 13 - Feb 27 2023) 16X237 Agile Development - Sprint Status#16X237AgileDevelopmentSprintStatus-Sprint204
|
Future Planning | Discussion Points: Planning for Mayo team in the coming fiscal year:
|
Technical Debt remediation |
|
CTS2 Mapping/URI Resolver | Discussion Points:
Decision Points: |
caDSR Query | Have been asking for other standalone terminologies, expected that they will use CTS2 |
Statistics Dashboard | Discussion Points:
Decision Points: |
Comparison/Mapping Tool | Discussion Points:
Decision Points: |
EVS transition to virtual machines | Discussion Points:
Decision Points: |
Report Exporter | Discussion Points:
Decision Points: |
AWS Cloud to be in Separate Account | Discussion Points
Decision Points: |
Team Absences | Mayo Team - Tracy off 16,17; Andrew off Feb 24 MSC - Leidos - Mark off Feb 14-24 Systems - |
EVS SERVICE AND ARCHITECTURE GROUP UPDATES | |
EVS Service and Architecture Group | Discussion Points:
Decision Points: |
DATA UPDATES | |
Data | Discussion Points:
Decision Points: |
BROWSER UPDATES | |
Browser | Discussion Points:
Decision Points: |
QA UPDATES | |
QA | Discussion Points: (see chart)
Decision Points: |
TERMINOLOGIES LIFECYCLE REPORT | |
Terminology Updates and Schedule Discussion Points: Decision Points: | |
Mark Benson TPM Update |
LexEVS Spring Migration Progress
Technical Debt Related Update | Estimated Effort | Status | Ticket |
---|---|---|---|
Code Inventory | 4 days | Complete | 2037998 |
Lexevs - update "easy" jars | 2 days | Complete | 2111723 |
Update ddlutils - research and design | 3 days | Complete | 2122958 |
Update ddltils - implementations | 10 days | In Progress | 2141127 |
Lexevs Unit testing | 2 days | 2141156 | |
CTS2 lexevs-service vulnerability update | 2 days | 2141189 | |
CTS2 unit testing | 2 days | 2141198 | |
QA Lexevs / CTS2 | 3 days | 2141217 | |
Repair QA issues | 2 days | ||
Deployment Lexevs / CTS2 | 5 days (elapsed) | 2141227 | |
Update LexEVS to Java 11 - research and design | 4 days | 2152899 | |
LexEVS Java 11 implementation | 5 days | 2152917 | |
lucene 9 - research and design | 8 days | 2145025 | |
lucene 9 - implementation | 15 days | 2145027 | |
LexEVS Java 11 unit testing | 3 days | 2152921 | |
CTS2 lexevs-service Java 11 - research and design | 3 days | 2152928 | |
CTS2 lexevs-service Java 11 implementation | 3 days | 2152932 | |
CTS2 unit testing | 2 days | 2152941 | |
QA Lexevs / CTS2 | 3 days | 2152945 | |
Repair QA issues | 2 days | 2153023 | |
Update Jenkins | 1 day | 2152947 | |
Deployment Lexevs / CTS2 | 10 days (elapsed) | 2152950 | |
lexevs-service-rest-docs vulnerability update design | 2 days | ||
lexevs-service-rest-docs vulnerability implementation | 4 days | ||
lexevs-service-rest-docs unit testing | 1 day | ||
lexevs-service-rest-docs QA | 1 day | ||
lexevs-service-rest-docs deployment | 4 days (elapsed) | ||
lexevs-service-rest-docs Java 11 design | 2 days | ||
lexevs-service-rest-docs Java 11 implementation | 3 days | ||
lexevs-service-rest-docs unit testing | 1 day | ||
lexevs-service-rest-docs QA | 1 day | ||
lexevs-system-test design | 4 days | ||
lexevs-system-test implementation | 6 days | ||
lexevs remaining dependency updates - design | 10 days | ||
lexevs remaining dependency updates - implementation | 20 days | ||
CTS2 remaining dependency updates - design | 1 day | ||
CTS2 remaining dependency updates - implementation | 3 days | ||
Unit testing | 2 days | ||
QA | 2 days | ||
Deployment | 5 days (elapsed) | ||
Total Effort (Approximately) | 104 days |
Technical Debt Related Update | Estimated Effort | Status |
---|---|---|
Report Exporter vulnerabilities - design | 4 days | |
Report Exporter vulnerabilities - implementation | 5 days | |
Unit testing | 2 days | |
QA | 2 days | |
Deployment | 5 days (elapsed) |
Vocabularies Slated for Production
Terminology Updates and Schedule
Vocabulary Name | Local Name | Version | Arrival Date | Loaded to data-qa DB | Date to Stage | Date to Production |
---|---|---|---|---|---|---|
Vocabulary Name in LexBIG | Short Name | Version identifier | Date the vocabulary arrived for processing | Has the vocabulary been loaded to the data-qa database? | Approximate date the vocabulary version is scheduled to move to staging | Approximate date the vocabulary version is scheduled to move to production |
NCI Thesaurus | NCIt | 23.01e | 01/31/2023 | yes | 02/09/23 | 2/10/23 |
NCIt-ChEBI | NCIt-ChEBI | Jan2023 | 01/31/2023 | yes | 02/09/23 | 2/10/23 |
NCIt-HGNC | NCIt-HGNC | Jan2023 | 01/31/2023 | yes | 02/09/23 | 2/10/23 |
SwissProt | SwissProt | Jan2023 | 01/31/2023 | yes | 02/09/23 | 2/10/23 |
ChEBI | ChEBI | |||||
GO | GO | |||||
HGNC | HGNC |
QA Schedule and Status
SECTION FOR FUNCTIONAL SYSTEM TESTING STATUS ::
Application and Version | Percentage Complete | Estimated Completion Date per Iteration | Priority Level | Type Of Testing | Current Tier for Release (DEV, QA, Stage, Prod) | Expected Production Date |
EVS REST API (v1.6) | 100% | 5/27/2022 | High | Progression + Regression | QA | 6/6/2022 |
EVS Explore (v1.6) | 100% | 5/27/2022 | High | Progression + Regression | QA | 6/6/2022 |
EVS REST API(v1.6) | 100% | 6/1/2022 | High | Regression | Stage | 6/6/2022 |
EVS Explore(v1.6) | 100% | 6/2/2022 | High | Regression | Stage | 6/7/2022 |
EVS REST API(22.05e) - Monthly Data Deployment | 100% | 6/1/2022 | High | Regression | Stage | 6/3/2022 |
EVS REST API(22.05e) - Monthly Data Deployment | 100% | 6/3/2022 | High | Regression | Production | 6/3/2022 |
EVS REST API(v1.6) | 100% | 6/6/2022 | High | Regression | Production | 6/6/2022 |
EVS Explore(v1.6) | 100% | 6/7/2022 | High | Regression | Production | 6/7/2022 |
NCIt,NCIm,TermForm(22.05e + GO & HGNC Jun 2022 Deployment) | 100% | 6/3/2022 | High | Regression | Stage | 6/6/2022 |
NCIt,NCIm,TermForm(22.05e + GO & HGNC Jun 2022 Deployment) | 100% | 6/6/2022 | High | Regression | Production | 6/8/2022 |
EVS REST API(22.06d) - Monthly Data Deployment | 100% | 6/30/2022 | High | Regression | Stage , Production | 6/30/2022 |
NCIt,NCIm,TermForm(22.06d) - Monthly Data Deployment | 100% | 7/8/2022 | High | Smoke | Stage,Production | 7/8/2022 |
NCIt,NCIm,TermForm(22.05e + GO & HGNC Jun 2022 Deployment) | 100% | 6/3/2022 | High | Regression | Stage | 6/6/2022 |
NCIt,NCIm,TermForm(22.06d) - Monthly Data Deployment | 100% | 7/8/2022 | High | Smoke | Stage,Production | 7/8/2022 |
NCIt,NCIm,TermForm(ChEBI, GO & HGNC July 2022 Deployment) | 100% | 7/12/2022 | High | Smoke | Stage | 7/12/2022 |
NCIt,NCIm,TermForm(ChEBI, GO & HGNC July 2022 Deployment) | 100% | 7/13/2022 | High | Smoke | Production | 7/13/2022 |
EVS REST API(22.07d) - Monthly Data Deployment | 100% | 7/27/2022 | High | Regression | Stage , Production | 7/27/2022 |
NCIt,NCIm,TermForm(22.07d) - Monthly Data Deployment | 100% | 8/1/2022 | High | Smoke | Stage,Production | 8/1/2022 |
NCIt,NCIm,TermForm(CanMED, GO & HGNC AUG 2022 Deployment) | 100% | 8/3/2022 | High | Smoke | Stage,Production | 8/3/2022 |
EVS REST API - 1.6.1 (Hot Fix Deployment) | 100 % | 8/3/2022 | Highest | Progression + Regression | Stage,Production | 8/4/2022 |
Attendees
Name | Role | Present |
---|---|---|
Remennik, Lyubov | NIH/NCI | |
Safran, Tracy | NIH/NCI [C] | |
Ong, Kim L | NIH/NCI [C] | |
Lucas, Jason R | NIH/NCI [C] | |
Bauer, Scott | NIH/NCI [C] | |
Alkis, Barry | NIH/NCI [C] | |
Solie, Chuck | NIH/NCI [C] | |
Truong, Tracy | NIH/NCI [C] | |
Kondareddy, Swathi | NIH/NCI [C] | |
Singh, Itendra | NIH/NCI [C] | |
Zhang, Chao | NIH/NCI [C] | |
Johnson, Connie | NIH/NCI [C] | |
Whiteman, Lori | NIH/NCI [C] | |
Benson, Mark | NIH/NCI [C] | |
Andrew Moore | NIH/NCI [C] |
JIRA Issues
Recent EVS Stats Dashboard Related Bugs and Features (within last week)
Recent Report Exporter Related Bugs and Features (within last week)
Recent LexEVS Related Bugs and Features (within last week)
Recent CTS2 Service Related Issues (within last week)
6.5 LexEVS Related Issues
6.5 CTS2 Service Related Issues