NIH | National Cancer Institute | NCI Wiki  

Agenda

EVS Discussion

Open System Tickets

Ticket Description Actions, Update
NCI-RITM0465063
NCI-INC0778085
MEME URI not working, hostname usable as workaround

Still working on escalating this issue. Contact made.  Being escalated to management

NCI-INC0805939
NCI-INC0805936
CTS2 down on Dev and QA
Met with Systems team to debug on Tu, Feb 27.
Waiting to hear back from Zihua on additional debugging work. 

NCI-RITM0512149

Security consult about IP traffic to Prod
Asked for dynamic IP throttling
NCI-INC0808122Report Exporter down on Stage
Closed. Opening another ticket (NCI-INC0810790 below)
NCI-INC0810790Report Exporter issue not avail on VPN
Open

NCI-RITM0513127

Give Zihua He access to apache logs
Having issues with collectors and access to logs

NCI-RITM0512409

Requesting access to the Report Exporter logs on the stage tier (nciws-s2284-c) to Andrew Moore
Open

NCI-RITM0513263

NCIt Jenkins not deployed on DataQA
Closed

NCI-RITM0513671

Deploy Report Exporter to STAGE
Closed

NCI-RITM0513820

Service account to access Datadog S3 bucket
Closed

NCI-RITM0507553

S3 Bucket for holding Datadog logs
Closed

SCTASK0852270

Old Java version (1.7) on processing server
Open - Tracy will work with Chao

 

Tomcat 9 installation on DEV
Open

SYSTEMS
EVS transition to virtual machines

STATUS:

Prod2 server up and running - being tested

  • DECIDED: conversion first, then transition to VMs.  Likely end of March
  • URLs documented List of EVS URLs



LEXEVS UPDATES

Monthly Planning and Focus

Completed Sprint - Sprint 217 (Feb 2 - Mar 4) -

Current Sprint  - Sprint 218 (Mar 5 - Mar 29) - Sprint 218

For the month of March 2024

  • Report Exporter

    • Start work on templating

  • Improvements, Refactoring Code Debt, Feature development:
  • Implementation of Java 17
  • DataDog
  • NCI Terms Browser
Technical Debt remediation

LexEVS Code Debt Refactoring - Java 17 refactoring currently is in progress

  • Tomcat 9 partially installed on Dev.  Waiting on Java 8 cts2 problems to be resolved before asking for completion
OS Updates
  • QA conversions starting - Dev,QA, Stage updated for LexEVS. Some issues with CTS2 being debugged
  • Protege and SIP in completed in Dev/QA/Stage
  • Kathy Coleman to notify when ready to go to Prod
Report Exporter
  • Working on templating starting
    • Doing phase 1 - updating description fields
  • Wait time indicator on Stage
    • Release notes written
  • Staging down, ticket entered
    • Works off VPN but not on VPN


Security

Notification 3/13 that lvg2015 on Processing server needs update as it relies on Java 7

Statistics Dashboard

OBJECTIVE 
Complete Migration of Statistics Dashboard from SumoLogic to DataDog by March 2024.  Hard end in April (ish) - possibly end of June

STATUS

  • S3 bucket has been created
    • Should be working now
    • Needs testing of archiving and refresh
  • RUM installation completed
  • Collectors installed on all servers except evs.nci.nih.gov 
  • No apache logs being pulled in for on-prem servers - Cyrus reaching out to DataDog support
    • Zihua He working on configuring

Link: Sharepoint Project Task Checklist

Comparison/Mapping Tool

On Hold

AWS Cloud to be in Separate Account

Waiting on AWS team

Team Absences


Mayo Team - 

MSC - Kim off March 15

Leidos - 

QA - 

Gov - 



EVS SERVICE AND ARCHITECTURE GROUP UPDATES
EVS Service and Architecture Group

EVS PROD Outage

  • Broken pipe issues on Prod - client being cut off before server completes query
    • Deployment of tag with removed old jars
    • Meeting with systems about throttling
  • Some remediation being made on Stage 2 to help with startup caching - increased CPUs
  • Contact Us page - decrease in priority.
    • CBIIT has possible solutions that we will wait upon


DATA UPDATES
Data
  • 24.02d on Prod as of yesterday
  • Monthlies on DataQA today
  • Meta starting next week
  • FTP issues - meeting with systems being arranged
    • Meta managed to be uploaded
    • Communicate with Lori to get information

BROWSER UPDATES

Browser
  • Met with systems to deal with Jenkins issue, now able to deploy
  • History page working per Scott, should have tag soon

QA UPDATES

QA
  • Reg on Report Exporter 2.01 on QA and Stage in progress
  • Data 24.02d completed on Stage on Prod
  • Testing legacy browsers next Monday

TERMINOLOGIES LIFECYCLE REPORT

Terminology Updates and Schedule 

Mark Benson TPM UpdateThanks to Systems for making lots of progress this week.


Vocabularies Slated for Production

  Terminology Updates and Schedule


Vocabulary Name

Local Name

Version

Arrival Date

Loaded to data-qa DB

Date to Stage

Date to Production

Vocabulary Name in LexBIG

Short Name

Version identifier

Date the vocabulary arrived for processing

Has the vocabulary been loaded to the data-qa database?

Approximate date the vocabulary version is scheduled to move to staging

Approximate date the vocabulary version is scheduled to move to production

NCI ThesaurusNCIt23.12d12/27/2023yes01/05/2401/09/24
NCIt-HGNCNCIt-HGNCJan202412/27/2023yes01/05/2401/09/24
SwissProtSwissProtJan202412/27/2023yes01/05/2401/09/24
ChEBIChEBIv22801/09/24yes01/12/2401/17/24
HGNCHGNCJan202401/09/24yes01/12/2401/17/24

QA Schedule and Status

see  QA Scheduling and Status



SECTION FOR FUNCTIONAL SYSTEM TESTING STATUS ::

Application and Version

Percentage Complete

Estimated Completion Date per Iteration

Priority Level 

Type Of Testing

Current Tier for Release (DEV, QA, Stage, Prod)

Expected Production Date

EVS REST API (v1.6)

100%

5/27/2022

High

Progression + Regression 

QA

6/6/2022

EVS Explore (v1.6)

100%

5/27/2022

High

Progression + Regression

QA

6/6/2022

EVS REST API(v1.6)

100%

6/1/2022

High

Regression

Stage

6/6/2022

EVS Explore(v1.6)

100%

6/2/2022

High

Regression

Stage

6/7/2022

EVS REST API(22.05e) - Monthly Data Deployment

100%

6/1/2022

High

Regression

Stage

6/3/2022

EVS REST API(22.05e) - Monthly Data Deployment

100%

6/3/2022

High

Regression

Production

6/3/2022

EVS REST API(v1.6)

100%

6/6/2022

High

Regression

Production

6/6/2022

EVS Explore(v1.6)

100%

6/7/2022

High

Regression

Production

6/7/2022

NCIt,NCIm,TermForm(22.05e + GO & HGNC Jun 2022 Deployment)

100%

6/3/2022

High

Regression

Stage

6/6/2022

NCIt,NCIm,TermForm(22.05e + GO & HGNC Jun 2022 Deployment)

100%

6/6/2022

High

Regression

Production

6/8/2022

EVS REST API(22.06d) - Monthly Data Deployment

100%

6/30/2022

High

Regression

Stage , Production

6/30/2022

NCIt,NCIm,TermForm(22.06d) - Monthly Data Deployment

100%

7/8/2022

High

Smoke

Stage,Production

7/8/2022

NCIt,NCIm,TermForm(22.05e + GO & HGNC Jun 2022 Deployment)

100%

6/3/2022

High

Regression

Stage

6/6/2022

NCIt,NCIm,TermForm(22.06d) - Monthly Data Deployment100%7/8/2022HighSmokeStage,Production7/8/2022
NCIt,NCIm,TermForm(ChEBI, GO & HGNC July 2022 Deployment)100%7/12/2022HighSmokeStage7/12/2022
NCIt,NCIm,TermForm(ChEBI, GO & HGNC July 2022 Deployment)100%7/13/2022HighSmokeProduction7/13/2022

EVS REST API(22.07d) - Monthly Data Deployment

100%

7/27/2022

High

Regression

Stage , Production

7/27/2022

NCIt,NCIm,TermForm(22.07d) - Monthly Data  Deployment100%8/1/2022HighSmokeStage,Production8/1/2022
NCIt,NCIm,TermForm(CanMED, GO & HGNC AUG 2022 Deployment)100%8/3/2022HighSmokeStage,Production8/3/2022

EVS REST API - 1.6.1 (Hot Fix Deployment)

100 %

8/3/2022

Highest

Progression + Regression

Stage,Production

8/4/2022


Attendees

Name

Role

Present

Remennik, LyubovNIH/NCIcheck mark button 

Safran, Tracy

NIH/NCI [C]
Ong, Kim LNIH/NCI [C]check mark button 
Lucas, Jason RNIH/NCI [C]check mark button 
Bauer, Scott  NIH/NCI [C]
Alkis, BarryNIH/NCI [C]<checked in>
Solie, ChuckNIH/NCI [C]
Kondareddy, SwathiNIH/NCI [C]check mark button
Singh, ItendraNIH/NCI [C]check mark button
Zhang, ChaoNIH/NCI [C]check mark button
Johnson, ConnieNIH/NCI [C]
Whiteman, LoriNIH/NCI [C]
Benson, MarkNIH/NCI [C]check mark button
Andrew MooreNIH/NCI [C]



JIRA Issues


Recent EVS Stats Dashboard Related Bugs and Features 

Key Summary T Created Reporter P Status
Loading...
Refresh

Recent Report Exporter Related Bugs and Features 

|

Key Summary T Created Reporter P Status
Loading...
Refresh

Recent LexEVS Related Bugs and Features 

Key Summary T Created Reporter P Status
Loading...
Refresh

Recent CTS2 Service Related Issues 

Key Summary T Created Updated Due Assignee Reporter P Status Resolution
Loading...
Refresh


ASSIGNED ACTION ITEMS

DescriptionDue dateAssigneeTask appears on
09 Oct 2023Benson, Mark (NIH/NCI) [C]LexEVS Meeting Minutes - 2023.10.25
  • Benson, Mark (NIH/NCI) [C] to schedule a mtg/ discuss a possible CSS file/ENV variable for banner message and report on  
11 Oct 2023Benson, Mark (NIH/NCI) [C]LexEVS Meeting Minutes - 2023.10.25
11 Oct 2023Benson, Mark (NIH/NCI) [C]LexEVS Meeting Minutes - 2023.10.25
  • Benson, Mark (NIH/NCI) [C] to schedule a mtg/ discuss a possible CSS file/ENV variable for banner message and report on  
11 Oct 2023Benson, Mark (NIH/NCI) [C]LexEVS Meeting Minutes - 2023.10.18
11 Oct 2023Benson, Mark (NIH/NCI) [C]LexEVS Meeting Minutes - 2023.10.18
  • Benson, Mark (NIH/NCI) [C] to schedule a mtg/ discuss a possible CSS file/ENV variable for banner message and report on  
11 Oct 2023Benson, Mark (NIH/NCI) [C]LexEVS Meeting Minutes - 2023.10.11
  • Benson, Mark (NIH/NCI) [C] to schedule a mtg/ discuss a possible CSS file/ENV variable for banner message and report on  
11 Oct 2023Benson, Mark (NIH/NCI) [C]LexEVS Meeting Minutes - 2023.10.04
Benson, Mark (NIH/NCI) [C]LexEVS Meeting Minutes - 2024.09.11
  • Get the Report ready and submitted this week
LexEVS Meeting Minutes - 2024.09.04
  • Mark to follow up on ticket status/ subproject structure
LexEVS Meeting Minutes - 2024.09.04
  • Mark to follow up on ticket status/ subproject structure
LexEVS Meeting Minutes - 2024.08.28
  • Mark to follow up on ticket status/ subproject structure
LexEVS Meeting Minutes - 2024.08.21
  • Mark to follow up on ticket status/ subproject structure
LexEVS Meeting Minutes - 2024.08.14
  • Tracy to ping for status
LexEVS Meeting Minutes - 2024.08.14
  • Tracy to send invite to systems to discuss migration in this meeting
LexEVS Meeting Minutes - 2024.07.17
  • Temporarily block Singapore traffic
LexEVS Meeting Minutes - 2024.06.05
  • Tracy to request shut down of instance to save resources
LexEVS Meeting Minutes - 2024.06.05
  • Temporarily block Singapore traffic
LexEVS Meeting Minutes - 2024.05.29
  • Tracy to request shut down
LexEVS Meeting Minutes - 2024.05.29
  • Check status of termform and Tomcat9
LexEVS Meeting Minutes - 2024.05.15



  • No labels