Page History
...
- Dates: April 22, 2015 – May 12, 2015 (3 weeks)
- Goal:
- Obtain NCI signoff on project documentation (as per SOW)
- Prepare the development environment for 6.3 RC2
- Resolve 6.3 JIRA issues prioritized for 6.3 deployment.
- Provide continued support and issue resolution.
- Project Roadmap
- Agile Board
- Report
- Retrospective
- DeliverablesTBD
Sprint 3
- Dates: April 8, 2015 – April 21, 2015
- Goal:
- Take what we learned from Sprint 2 and revise the roadmap to better reflect the development plan.
- Obtain NCI signoff on project documentation (as per SOW)
- Prepare the development environment (GIT and Fisheye)
- Provide continued support and issue resolution.
- Project Roadmap
...