This is the UAT and deployment schedule as of 1/12/2017
Activity | Start Date | End Date |
---|---|---|
Development on RC1 based on accumulated feedback and bug reports | Jan 9 | Feb 17 |
Editor training sessions | Feb 23 | Feb 24 |
UAT | Feb 27 | Mar 3 |
Bug fixes based on UAT | Mar 17 | |
QA | Mar 31 | |
Go/No go | Mar 31 | |
Protege 3.x Prompt and OWL baseline export | Apr 3 | |
Conversion of OWL1 to OWL2 | Apr 3 | Apr 5 |
Dual editing | Apr 6 | May 4 |