Contents of this Page
Sprint 15
- Dates: October 15, 2015 – October 28, 2015 (2 weeks)
- Goal:
- Demonstrate all previous LexEVS functionality as implemented with the new Lucene and 100% of unit test pass
- Provide continued support and issue resolution.
- Provide deployment support.
- Project Roadmap
- Pending
- Agile Board
- Sprint Report (includes issues/deliverables)
- Pending
- Retrospective
- Pending
Sprint 14
- Dates: October 1, 2015 – October 14, 2015 (2 weeks)
- Goal:
- Demonstrate all previous LexEVS functionality as implemented with the new Lucene and 100% of unit test pass
- Provide continued support and issue resolution.
- Provide deployment support.
- Project Roadmap
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- Artifacts
- v6.3.x branch
- Git tag: SNAPSHOT.V.6.3.0.SPRINT14.2015.10.15
- https://cbiit-download.nci.nih.gov/evs/LexEVS/v6.3/Release/lbRuntime_SNAPSHOT.V.6.3.0.SPRINT14.2015.10.15.jar
- Functionality Summary
- LEXEVS-1195 lbGUI provides drop down lists for a variety of content loading convenience. These content loading aides typically require a conventional coding scheme. Since resolve value sets are coding schemes under the covers, these also appear in the drop down lists. The number of these value sets loaded by some users creates a long list that is unusable under some circumstances. This snapshot removes the resolved value sets from the list.
- LEXEVS-1192 The OBI source is written in OWL2 format. It features Axioms that contain references to property annotations also defined in the source. When these property annotations are defined as owl literals they were being loaded properly. However most of the annotations were defined as simple IRI's and were not being properly loaded. This fix corrects that issue and provides test source and Unit tests to track for regression errors.
- Lucene branch
- Git Tag: SNAPSHOT.LUCENE.SPRINT14.2015.10.15
- http://cbiit-download.nci.nih.gov/evs/LexEVS/v6.4/lbRuntime_SNAPSHOT.LUCENE.SPRINT14.2015.10.15.jar
- Functionality Summary:
- Lucene queries on most multi property designations are functioning properly
- Lucene queries against a non-child status value are corrected.
- v6.3.x branch
Sprint 13
- Dates: September 17, 2015 – September 30, 2015 (2 weeks)
- Goal:
- Demonstrate functionality of some searches being performed in the API and 25% of functionality implemented.
- Provide continued support and issue resolution.
- Provide deployment support.
- Project Roadmap
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- Artifacts
- Git Tag: SNAPSHOT.SPRINT13.2015.09.29
- http://cbiit-download.nci.nih.gov/evs/LexEVS/v6.4/lbRuntime_SNAPSHOT.SPRINT13.2015.09.29.jar
- Functionality Summary
- Search Functions in matching designations for all search algorithms should return results.
- Sorting mechanisms seem to be in order according to limited Unit test application.
- Search API for mapping schemes should be as fully functional as other searches
- Some property restrictions are working within limitations. We are still working to fix concept status and property type restrictions – others are not fully tested.
- Multiple restrictions have limited functionality. Not fully tested.
Sprint 12
- Dates: September 3, 2015 – September 16, 2015 (2 weeks)
- Goal:
- Demonstrate functionality of some searches being performed in the API and 25% of functionality implemented.
- Provide continued support and issue resolution.
- Provide deployment support.
- Project Roadmap
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
Sprint 11
- Dates: August 20, 2015 – September 2, 2015 (2 weeks)
- Goal:
- Demonstrate functionality of some searches being performed in the API and 25% of functionality implemented.
- Provide continued support and issue resolution.
- Provide deployment support.
- Project Roadmap
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
Sprint 10
- Dates: August 06, 2015 – August 19, 2015 (2 weeks)
- Goal:
- Demonstrate functionality of some searches being performed in the API and 25% of functionality implemented.
- Provide continued support and issue resolution.
- Provide deployment support.
- Project Roadmap
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
Sprint 9
- Dates: July 23, 2015 – August 5, 2015 (2 weeks)
- Goal:
- Demonstrate functionality of some searches being performed in the API and 25% of functionality implemented.
- Provide continued support and issue resolution.
- Provide deployment support.
- Project Roadmap
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
Sprint 8
- Dates: July 9, 2015 – July 22, 2015 (2 weeks)
- Goal:
- All internal interfaces and code structure in place and documented.
- Demonstrate viability of the new Lucene approach with multi-indexes.
- Provide continued support and issue resolution.
- Provide deployment support.
- Project Roadmap
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
Sprint 7
- Dates: June 25, 2015 – July 8, 2015 (2 weeks)
- Goal:
- Demonstrate viability of the new Lucene approach and update of all dependencies.
- Provide continued support and issue resolution.
- Provide deployment support.
- Project Roadmap
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
Sprint 6
- Dates: June 3, 2015 – June 23, 2015 (3 weeks)
- Goal:
- Demonstrate viability of the new Lucene approach and update of all dependencies.
- Provide continued support and issue resolution.
- Provide deployment support.
- Project Roadmap
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
Sprint 5
- Dates: May 13, 2015 – June 2, 2015 (3 weeks)
- Goal:
- Demonstrate viability of the new Lucene approach and update of all dependencies.
- Provide continued support and issue resolution.
- Provide deployment support.
- Project Roadmap
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
Sprint 4
- Dates: April 22, 2015 – May 12, 2015 (3 weeks)
- Goal:
- Obtain NCI signoff on project documentation (as per SOW)
- Prepare the development environment for 6.3 RC2
- Resolve 6.3 JIRA issues prioritized for 6.3 deployment.
- Provide continued support and issue resolution.
- Project Roadmap
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
Sprint 3
- Dates: April 8, 2015 – April 21, 2015
- Goal:
- Take what we learned from Sprint 2 and revise the roadmap to better reflect the development plan.
- Obtain NCI signoff on project documentation (as per SOW)
- Prepare the development environment (GIT and Fisheye)
- Provide continued support and issue resolution.
- Project Roadmap
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective